Sparely
DU

SPRING,SAFETY VALVE,MODEL XY234,VITON

Material 4100066116 · SPRING · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100066116
Category
SPRING
Base unit
EA
MRP type
Non Stock
Criticality
A (4 of 7 FuncLocs A/B, 5 safety/shutdown valve)
Supplier
No PO history
Lead time
137 d · P80 196 d
Unit price
Rp 8.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 5 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~137 days; expected demand during lead time 0.4.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
  • 6.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 35.3M · order by 01 Oct 2026
Expected arrival ≈ 137 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.9%
stockout risk now 31%
Unit price
Rp 8.8M
Category + unit estimate
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 283 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 7 functional locations

4 with criticality A/B · 9 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_PRV-643
SAFETY VALVE HE-164A
A100.04
PX_PRV-1383B
SAFETY VALVE PP-1694A
B100.04
PX_PRV-997A
SAFETY VALVE BF-105
C300.04
PX_PRV-182
SAFETY VALVE PP-507
S100.04
PX_PRV-1866D
SAFETY VALVE PP-506A
S100.04

Lead time and procurement

Lead time 137 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
04 Jan 2026MediumPX_KT-513KT-513 governor valve hunting
03 May 2025MediumPX_KT-513KT-513 governor valve hunting

Recent goods issues

Posting dateQtyOrderOrder type
22 Dec 20251201000029657Corrective