SPRING,SAFETY VALVE,TYPE HO480,A182F11
Material 4100066120 · SPRING · Plant 1000
ASafety-criticalLong-leadReorderNormalSlow-moving
- Material
- 4100066120
- Category
- SPRING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 6 FuncLocs A/B, 3 safety/shutdown valve)
- Supplier
- KARYA ENERGI SENTOSA PT
- Lead time
- 127 d · P80 196 d
- Unit price
- Rp 15.9M
Recommendation
- 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 2.1 EA/year: 2.1 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~127 days; expected demand during lead time 0.7.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
- 5.On hand 3 + on order 0 is at or below the reorder point: order 3 now.
- 6.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 47.7M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Safety-critical (SCE)Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 1%
Unit price
Rp 15.9M
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 402 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.
Installed on 6 functional locations
4 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_PRV-271B SAFETY VALVE HE-391 | A | 1 | 0 | 0.04 |
| PX_PRV-658 SAFETY VALVE KC-551D | S | 3 | 0 | 0.04 |
| PX_PRV-984B SAFETY VALVE HE-1287D | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 127 ± 65 days (PO history + category, 1 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 02 Apr 2026 | PR03 Regular replenishment | 1 | Rp 15.9M | 06 Jul 2026 | 95 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
| 14 May 2026 | Low | PX_KT-397A | KT-397A trip test |
| 03 Apr 2026 | Medium | PX_KT-419A | KT-419A steam leak at gland |
| 02 Apr 2026 | Medium | PX_KT-397A | Follow up after steam upset KT-397A |
| 17 Mar 2026 | Medium | PX_KT-419A | Install cover plate for MCP cracking |
| 20 Nov 2025 | Medium | PX_KT-419A | Leak from packing |
| 10 Nov 2025 | Medium | PX_KT-419A | Painting KT-419A |
| 03 Sept 2025 | Medium | PX_KT-419A | Follow up after steam upset KT-419A |
| 15 May 2025 | Low | PX_KT-419A | PSM25/Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Aug 2025 | 1 | 201000039654 | Corrective |