Sparely
DU

SPRING,SAFETY VALVE,TYPE HO480,A182F11

Material 4100066120 · SPRING · Plant 1000

ASafety-criticalLong-leadReorderNormalSlow-moving
Material
4100066120
Category
SPRING
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 6 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
127 d · P80 196 d
Unit price
Rp 15.9M

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 2.1 EA/year: 2.1 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~127 days; expected demand during lead time 0.7.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 5.On hand 3 + on order 0 is at or below the reorder point: order 3 now.
  • 6.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 47.7M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Safety-critical (SCE)Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 1%
Unit price
Rp 15.9M
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 402 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 6 functional locations

4 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_PRV-271B
SAFETY VALVE HE-391
A100.04
PX_PRV-658
SAFETY VALVE KC-551D
S300.04
PX_PRV-984B
SAFETY VALVE HE-1287D
S100.04

Lead time and procurement

Lead time 127 ± 65 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
02 Apr 2026PR03
Regular replenishment
1Rp 15.9M06 Jul 202695 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026LowPX_KT-397AKT-397A trip test
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
02 Apr 2026MediumPX_KT-397AFollow up after steam upset KT-397A
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A
15 May 2025LowPX_KT-419APSM25/Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
25 Aug 20251201000039654Corrective