SPRING,SAFETY VALVE,MODEL SO505,VITON

Material 4100066628 · SPRING · Plant 1000

ASafety-criticalLong-leadMonitorSlow-moving
Material
4100066628
Category
SPRING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 4 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
TIRTA SEJAHTERA PERSADA PT
Lead time
133 d · P80 196 d
Unit price
Rp 13.5M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 3.8 EA/year: 3.8 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~133 days; expected demand during lead time 1.4.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
  • 5.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Long-leadSingle source
On hand / on order
8 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
9
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 13.5M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 294 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 4 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KT-383A
TURBINE FOR KC-383A
S173.67
PX_PRV-991D
SAFETY VALVE HE-935A
S100.04

Lead time and procurement

Lead time 133 ± 65 days (PO history + category, 1 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
13 Mar 2026PR03
Regular replenishment
1Rp 13.5M12 Jul 2026121 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
24 May 2026HighPX_KT-383AKT-383A steam leak at gland
13 May 2026LowPX_KT-447KT-447 trip test

Recent goods issues

Posting dateQtyOrderOrder type
11 Dec 20251201000033790Corrective