SPRING,SAFETY VALVE,MODEL SO505,VITON
Material 4100066628 · SPRING · Plant 1000
ASafety-criticalLong-leadMonitorSlow-moving
- Material
- 4100066628
- Category
- SPRING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 4 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- TIRTA SEJAHTERA PERSADA PT
- Lead time
- 133 d · P80 196 d
- Unit price
- Rp 13.5M
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 3.8 EA/year: 3.8 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~133 days; expected demand during lead time 1.4.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
- 5.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Long-leadSingle source
On hand / on order
8 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
9
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 13.5M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 294 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 6.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.
Installed on 4 functional locations
1 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-447 TURBINE FOR KC-447 | S | 1 | 13 | 6.24 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_PRV-991D SAFETY VALVE HE-935A | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 133 ± 65 days (PO history + category, 1 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Mar 2026 | PR03 Regular replenishment | 1 | Rp 13.5M | 12 Jul 2026 | 121 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 13 May 2026 | Low | PX_KT-447 | KT-447 trip test |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 11 Dec 2025 | 1 | 201000033790 | Corrective |