SPRING,SAFETY VALVE,SIZE WL212,INCOLOY

Material 4100066670 · SPRING · Plant 1000

ASafety-criticalReduceNon-moving
Material
4100066670
Category
SPRING
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 4 FuncLocs A/B, 3 safety/shutdown valve)
Supplier
No PO history
Lead time
137 d · P80 196 d
Unit price
Rp 8.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 3.Lead time ~137 days; expected demand during lead time 0.1.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 5.Stock 34 exceeds the level to keep (2) by 32.
  • 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
34 / 0
no open PO
Today Min / Max
10 / 17
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 8.8M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 226.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 4 functional locations

1 with criticality A/B · 10 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-913
SAFETY VALVE HE-1593C
A200.04
PX_KT-264A
TURBINE FOR KC-264A
S342.39
PX_PRV-1319D
SAFETY VALVE HE-1277C
S130.90
UT_PRV-250B
SAFETY VALVE PP-745
S400.04

Lead time and procurement

Lead time 137 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
06 Sept 2026LowPX_PRV-1319DReplace lamp as per PM finding
01 Jul 2026LowPX_PRV-1319DPRV-1319D passing
11 Jun 2026LowPX_KT-264ALeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
21 Oct 2025MediumPX_KT-264AKT-264A governor valve hunting
31 May 2025MediumPX_KT-264AInstall scaffolding at KT-264A
20 May 2025LowPX_PRV-1319DLeak from packing

Recent goods issues

Never issued in the 17-month history.