SPRING,SAFETY VALVE,SIZE JR376,VITON

Material 4100066992 · SPRING · Plant 1000

ASafety-criticalLong-leadReduceSlow-moving
Material
4100066992
Category
SPRING
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 2 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
SURYA ENERGI JAYA PT
Lead time
110 d · P80 196 d
Unit price
Rp 8.7M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.7 EA/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~110 days; expected demand during lead time 0.2.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 5.Stock 35 exceeds the level to keep (3) by 32.
  • 6.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
35 / 1
next delivery 22 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 8.7M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 213 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 2 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_PRV-1300
SAFETY VALVE HE-874B
A400.04

Lead time and procurement

Lead time 110 ± 65 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
18 Aug 2026PR06
Regular replenishment
1Rp 8.7M22 Nov 2026
open
96 d
17 Feb 2026PR06
Regular replenishment
1Rp 8.8M30 Mar 202641 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
04 Jan 2026MediumPX_KT-513KT-513 governor valve hunting
03 May 2025MediumPX_KT-513KT-513 governor valve hunting

Recent goods issues

Posting dateQtyOrderOrder type
02 Mar 20261204000008865Preventive