Sparely
DU

SPRING,SAFETY VALVE,TYPE LC636,GRAPHITE

Material 4100067297 · SPRING · Plant 1000

ASafety-criticalLong-leadReorderCriticalStockout
Material
4100067297
Category
SPRING
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 3 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
142 d · P80 196 d
Unit price
Rp 12.6M

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.8 EA/year: 1.8 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~142 days; expected demand during lead time 0.7.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 8.
  • 5.On hand 0 + on order 3 is at or below the reorder point: order 5 now.
  • 6.Long lead time: 80% of deliveries took up to 196 days and the fastest seen in its category 77 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
5 EA
Rp 62.8M · order by 01 Oct 2026
Expected arrival ≈ 142 days
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
0 / 3
next delivery 19 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
8
order qty 2
Service level
100.0%
stockout risk now 5%
Unit price
Rp 12.6M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 261 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~77 days.

Installed on 3 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_PRV-319
SAFETY VALVE VD-538A
A100.04
PX_KT-264A
TURBINE FOR KC-264A
S142.39
PY_PRV-1263A
SAFETY VALVE HE-1008A
S100.04

Lead time and procurement

Lead time 142 ± 65 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
07 Jun 2026PR03
Regular replenishment
2Rp 12.7M09 Dec 2026
open
185 d
13 Oct 2025PR04
Regular (other)
1Rp 12.6M19 Nov 2026
open
402 d
20 Sept 2025PR06
Regular replenishment
1Rp 12.3M12 Jan 2026114 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Jun 2026LowPX_KT-264ALeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
21 Oct 2025MediumPX_KT-264AKT-264A governor valve hunting
31 May 2025MediumPX_KT-264AInstall scaffolding at KT-264A

Recent goods issues

Posting dateQtyOrderOrder type
13 Jan 20262201000021923Corrective