DISC,SAFETY VALVE,SIZE JD552,CS

Material 4100067939 · DISC · Plant 1000

BSafety-criticalReorderCriticalStockout
Material
4100067939
Category
DISC
Base unit
EA
MRP type
Non Stock
Criticality
B (1 of 6 FuncLocs A/B, 6 safety/shutdown valve)
Supplier
No PO history
Lead time
88 d · P80 171 d
Unit price
Rp 12.5M (est.)

Recommendation

  • 1.Safety-critical element: installed on 6 safety or shutdown valve location(s) (equipment criticality B). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~88 days; expected demand during lead time 0.1.
  • 4.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 2 now.
  • 6.Installed on 6 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
2 EA
Rp 25.1M · order by 01 Oct 2026
Expected arrival ≈ 88 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.6%
stockout risk now 9%
Unit price
Rp 12.5M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 282 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 350.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.

Installed on 6 functional locations

1 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-227
SAFETY VALVE PP-779A
B100.04
PX_PRV-720B
SAFETY VALVE HE-1164D
S110.47
PX_PRV-1442
SAFETY VALVE VD-1610
S100.04
PX_PRV-1448
SAFETY VALVE PP-752B
S100.04
PX_PRV-868
SAFETY VALVE VD-1167
S100.04
PY_PRV-874A
SAFETY VALVE VD-958
S100.04

Lead time and procurement

Lead time 88 ± 64 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Jun 2025LowPX_PRV-720BPRV-720B passing

Recent goods issues

Posting dateQtyOrderOrder type
23 Dec 20251201000027054Corrective