DISC,SAFETY VALVE,SIZE OT516,SS304
Material 4100067997 · DISC · Plant 1000
ASafety-criticalReorderNormalBelow reorder point
- Material
- 4100067997
- Category
- DISC
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 6 FuncLocs A/B, 6 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 88 d · P80 171 d
- Unit price
- Rp 12.5M (est.)
Recommendation
- 1.Safety-critical element: installed on 6 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 5.0 EA/year: 5.0 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~88 days; expected demand during lead time 1.2.
- 4.A 98.2% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 12.
- 5.On hand 3 + on order 0 is at or below the reorder point: order 9 now.
- 6.Installed on 6 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
9 EA
Rp 112.9M · order by 01 Oct 2026
Expected arrival ≈ 88 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
12
order qty 6
Service level
98.2%
stockout risk now 18%
Unit price
Rp 12.5M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 179 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 777.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~44 days.
Installed on 6 functional locations
1 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PRV-544A SAFETY VALVE PP-598B | A | 1 | 0 | 0.04 |
| PX_PRV-865 SAFETY VALVE HE-1008A | C | 1 | 0 | 0.04 |
| PX_PRV-718D SAFETY VALVE KC-369B | S | 1 | 4 | 1.75 |
| PX_PRV-742A SAFETY VALVE KC-582B | S | 1 | 1 | 0.04 |
| PX_PRV-1787 SAFETY VALVE PP-1121 | S | 1 | 0 | 0.04 |
| PX_PRV-1863A SAFETY VALVE VD-1641A | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 88 ± 64 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 23 Sept 2026 | Low | PX_PRV-718D | [MSI-B-26-KCJ-360/M] Replace line |
| 14 Sept 2026 | High | PX_PRV-718D | Replace lamp as per PM finding |
| 17 Jul 2026 | Low | PX_PRV-718D | PRV-718D simmering |
| 13 Jun 2025 | Medium | PX_PRV-718D | Leak from packing |
| 30 May 2025 | Low | PX_PRV-742A | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 05 Apr 2026 | 6 | 201000023956 | Corrective |