NOZZLE,SAFETY VALVE,MODEL FS613,SS316
Material 4100069634 · NOZZLE · Plant 1000
ASafety-criticalLong-leadReorderCriticalStockout
- Material
- 4100069634
- Category
- NOZZLE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (4 of 13 FuncLocs A/B, 13 safety/shutdown valve)
- Supplier
- KARYA SARANA GLOBAL PT
- Lead time
- 129 d · P80 177 d
- Unit price
- Rp 6.5M
Recommendation
- 1.Safety-critical element: installed on 13 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 3.5 EA/year: 3.5 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~129 days; expected demand during lead time 1.2.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 10.
- 5.On hand 0 + on order 7 is at or below the reorder point: order 3 now.
- 6.Long lead time: 80% of deliveries took up to 177 days and the fastest seen in its category 69 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 13 FuncLoc(s), 4 of them criticality A/B.
- 8.ML early warning: 53% probability of demand in the next 90 days.
Proposed purchase requisition
3 EA
Rp 19.6M · order by 01 Oct 2026
Expected arrival ≈ 129 days
Safety-critical (SCE)Long-leadML early warningConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 7
next delivery 08 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
10
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 6.5M
PO history
ML early warning: 53% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 159 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.
Installed on 13 functional locations
4 with criticality A/B · 16 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PRV-1448A SAFETY VALVE VD-664B | A | 2 | 0 | 0.04 |
| PX_PRV-1606B SAFETY VALVE HE-1422A | A | 1 | 0 | 0.04 |
| PX_PRV-305 SAFETY VALVE VD-996 | A | 1 | 0 | 0.04 |
| PX_PRV-544A SAFETY VALVE PP-598B | A | 1 | 0 | 0.04 |
| PX_PRV-1360B SAFETY VALVE PP-1171 | C | 2 | 0 | 0.04 |
| PX_PRV-822 SAFETY VALVE PP-1471A | C | 1 | 0 | 0.04 |
| PX_PRV-887 SAFETY VALVE HE-826 | S | 1 | 3 | 1.33 |
| PX_PRV-1439D SAFETY VALVE KC-372D | S | 1 | 0 | 0.04 |
| PX_PRV-1854A SAFETY VALVE VD-1695D | S | 1 | 0 | 0.04 |
| PX_PRV-243 SAFETY VALVE PP-442A | S | 1 | 0 | 0.04 |
| PX_PRV-275 SAFETY VALVE KC-717 | S | 1 | 0 | 0.04 |
| PX_PRV-463C SAFETY VALVE VD-123A | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 129 ± 50 days (PO history + category, 2 PO lines) · on-time 18%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 04 Aug 2026 | PR06 Regular replenishment | 3 | Rp 6.5M | 06 Jan 2027 open | 155 d |
| 03 Aug 2026 | PR06 Regular replenishment | 1 | Rp 6.5M | 08 Dec 2026 open | 127 d |
| 01 Nov 2025 | PR05 Project / turnaround | 3 | Rp 6.9M | 08 Feb 2028 open | 829 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 05 Feb 2026 | Medium | PX_PRV-887 | Replace lamp as per PM finding |
| 26 Jan 2026 | Low | PX_PRV-887 | PRV-887 passing |
| 25 Jun 2025 | Medium | PX_PRV-887 | PRV-887 passing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Apr 2026 | 1 | 201000008643 | Corrective |
| 05 Feb 2026 | 2 | 201000010658 | Corrective |
| 25 Dec 2025 | 2 | 201000011308 | Corrective |
| 25 Dec 2025 | 1 | 201000011308 | Corrective |
| 07 Dec 2025 | 1 | 201000037821 | Corrective |