Sparely
DU

NOZZLE,SAFETY VALVE,SIZE JF708,PTFE

Material 4100070046 · NOZZLE · Plant 1000

ASafety-criticalLong-leadReorderCriticalStockout
Material
4100070046
Category
NOZZLE
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 2 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
130 d · P80 177 d
Unit price
Rp 23.8M

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.6 EA/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~130 days; expected demand during lead time 0.2.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
  • 6.Long lead time: 80% of deliveries took up to 177 days and the fastest seen in its category 69 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 71.4M · order by 01 Oct 2026
Expected arrival ≈ 130 days
Safety-critical (SCE)Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 18%
Unit price
Rp 23.8M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 66 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 836.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.

Installed on 2 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-570A
SAFETY VALVE PP-481A
A130.47
PX_PRV-114
SAFETY VALVE VD-1252
S100.04

Lead time and procurement

Lead time 130 ± 50 days (PO history + category, 1 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
19 Nov 2025PR03
Regular replenishment
2Rp 23.8M25 Apr 2026157 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Jul 2026HighPX_PRV-570AInstall scaffolding at PRV-570A
06 Mar 2026MediumPX_PRV-570AInstall scaffolding at PRV-570A
01 Jun 2025LowPX_PRV-570APRV-570A simmering

Recent goods issues

Posting dateQtyOrderOrder type
27 Jul 20261201000021629Corrective