NOZZLE,SAFETY VALVE,SIZE BC204,NBR
Material 4100070150 · NOZZLE · Plant 1000
- Material
- 4100070150
- Category
- NOZZLE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- S (0 of 2 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 121 d · P80 177 d
- Unit price
- Rp 20.3M (est.)
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 1.2 EA/year: 1.2 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~121 days; expected demand during lead time 0.4.
- 4.A 98.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 688.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.
Installed on 2 functional locations
0 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PRV-1146 SAFETY VALVE PP-376 | S | 1 | 0 | 0.04 |
| PY_PRV-1528 SAFETY VALVE CL-1326 | S | 1 | 0 | 0.04 |
Lead time and procurement
Lead time 121 ± 50 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Dec 2025 | 4 | 201000001503 | Corrective |
| 28 Aug 2025 | 1 | 201000032683 | Corrective |