NOZZLE,SAFETY VALVE,SIZE RK669,INCOLOY

Material 4100070815 · NOZZLE · Plant 1000

SSafety-criticalLong-leadMaintainInsurance gap
Material
4100070815
Category
NOZZLE
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
LANGIT TEKNOLOGI PERSADA PT
Lead time
141 d · P80 177 d
Unit price
Rp 7.5M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 3.Lead time ~141 days; expected demand during lead time 0.0.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 5.Long lead time: 80% of deliveries took up to 177 days and the fastest seen in its category 69 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 09 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 7.5M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-819
SAFETY VALVE PP-326A
S100.04

Lead time and procurement

Lead time 141 ± 50 days (PO history + category, 1 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
21 Apr 2026PR06
Regular replenishment
1Rp 7.5M09 Nov 2026
open
202 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Never issued in the 17-month history.