NOZZLE,SAFETY VALVE,MODEL CO774,GRAPHITE

Material 4100071125 · NOZZLE · Plant 1000

SSafety-criticalLong-leadReorderCriticalStockout
Material
4100071125
Category
NOZZLE
Base unit
EA
MRP type
Non Stock
Criticality
S (0 of 1 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
123 d · P80 149 d
Unit price
Rp 48.3M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s) (equipment criticality S). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~123 days; expected demand during lead time 0.5.
  • 4.A 98.7% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
  • 5.On hand 0 + on order 2 is at or below the reorder point: order 4 now.
  • 6.Long lead time: 80% of deliveries took up to 149 days and the fastest seen in its category 69 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
Proposed purchase requisition
4 EA
Rp 193.0M · order by 01 Oct 2026
Expected arrival ≈ 123 days
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 27 Jan 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
98.7%
stockout risk now 16%
Unit price
Rp 48.3M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 22 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 753.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~69 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PRV-1661B
SAFETY VALVE KC-426D
S100.04

Lead time and procurement

Lead time 123 ± 45 days (PO history, 3 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
21 Aug 2026PR06
Regular replenishment
2Rp 47.4M27 Jan 2027
open
159 d
07 May 2026PR06
Regular replenishment
2Rp 48.3M26 Jul 202680 d
13 Sept 2025PR03
Regular replenishment
1Rp 50.1M24 Jan 2026133 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
09 Sept 20262201000016998Corrective
09 Sept 20261201000016998Corrective