FIREBRICK,INSUL,26,76T,114W,230L
Material 4100071521 · FIREBRICK · Plant 1000
ALong-leadMonitorStockout
- Material
- 4100071521
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (14 of 19 FuncLocs A/B)
- Supplier
- KARYA SEJAHTERA NUSANTARA PT
- Lead time
- 79 d · P80 113 d
- Unit price
- Rp 186,830
Recommendation
- 1.Forecast 42,409 EA/year: 42,409 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~79 days; expected demand during lead time 9,214.
- 3.A 99.0% service level gives the lowest holding + downtime-risk cost: reorder at 24,036, order up to 27,571.
- 4.Long lead time: 80% of deliveries took up to 113 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 19 FuncLoc(s), 14 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 7,950Single sourceAbnormal consumptionOpen POSame description as 6 other material numbers
On hand / on order
0 / 211,871
next delivery 09 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
24,036
safety stock 14,823
Rec. Max
27,571
order qty 3,535
Service level
99.0%
stockout risk now 0%
Unit price
Rp 186,830
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 45 issue days in the last 180 days, last issue 9 days ago, 124 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 16 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9,000 units) excluded from the baseline.
Demand pattern Smooth · 149 issue days · 34 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 77.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 19 functional locations
14 with criticality A/B · 29,358 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 400 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 5,037 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1,500 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 50 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 400 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 400 | 29 | 11.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 5,037 | 28 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 120 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1,500 | 23 | 9.01 |
| PX_BF-105-PD33 QO TO QUENCH FITTING | A | 120 | 2 | 1.30 |
| PX_BF-104-BRN03 DILUTION STEAM TO MIXED FEED COIL | A | 5,037 | 0 | 0.45 |
| PX_BF-105-DUCT29 COIL OUTLET BF-105 | A | 120 | 0 | 0.45 |
Lead time and procurement
Lead time 79 ± 50 days (PO history, 36 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 03 Sept 2026 | PR06 Regular replenishment | 31,241 | Rp 192,468 | 09 Oct 2026 open | 36 d |
| 25 Aug 2026 | PR06 Regular replenishment | 39,621 | Rp 192,308 | 11 Nov 2026 open | 78 d |
| 10 Aug 2026 | PR01 Import / long-lead | 40,598 | Rp 182,765 | 13 Dec 2026 open | 125 d |
| 31 Jul 2026 | PR06 Regular replenishment | 30,209 | Rp 184,313 | 15 Sept 2026 | 46 d |
| 29 Jul 2026 | PR06 Regular replenishment | 55,801 | Rp 195,042 | 07 Sept 2026 | 40 d |
| 16 Jun 2026 | PR05 Project / turnaround | 59,634 | Rp 192,193 | 24 Nov 2026 open | 161 d |
| 12 Jun 2026 | PR06 Regular replenishment | 52,466 | Rp 189,047 | 19 Aug 2026 | 68 d |
| 04 Jun 2026 | PR05 Project / turnaround | 37,855 | Rp 180,663 | 04 Aug 2026 | 61 d |
| 02 Jun 2026 | PR06 Regular replenishment | 56,530 | Rp 182,769 | 02 Aug 2026 | 61 d |
| 30 May 2026 | PR06 Regular replenishment | 41,935 | Rp 184,671 | 08 Jul 2026 | 39 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Sept 2026 | 50 | 201000039118 | Corrective |
| 21 Sept 2026 | 200 | 201000022167 | Corrective |
| 19 Sept 2026 | 50 | 204000022416 | Preventive |
| 11 Sept 2026 | 50 | 204000013108 | Preventive |
| 08 Sept 2026 | 200 | 201000035941 | Corrective |
| 05 Sept 2026 | 5,700 | 201000000202 | Corrective |
| 03 Sept 2026 | 50 | 201000031484 | Corrective |
| 29 Aug 2026 | 1,500 | 201000018854 | Corrective |
| 27 Aug 2026 | 200 | 201000001746 | Corrective |
| 25 Aug 2026 | 600 | 201000011526 | Corrective |
| 24 Aug 2026 | 50 | 201000000994 | Corrective |
| 10 Aug 2026 | 50 | 201000001248 | Corrective |
| 10 Aug 2026 | 1,500 | 204000007036 | Preventive |
| 31 Jul 2026 | 1,500 | 204000016683 | Preventive |
| 27 Jul 2026 | 200 | 201000009720 | Corrective |