FIREBRICK,INSUL,28,65T,114W,230L
Material 4100071552 · FIREBRICK · Plant 1000
ALong-leadMonitorStockout
- Material
- 4100071552
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (12 of 16 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 84 d · P80 118 d
- Unit price
- Rp 190,717
Recommendation
- 1.Forecast 29,012 EA/year: 29,012 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~84 days; expected demand during lead time 6,709.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 18,792, order up to 21,210.
- 4.Long lead time: 80% of deliveries took up to 118 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 16 FuncLoc(s), 12 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 4,950Single sourceAbnormal consumptionOpen POSame description as 9 other material numbers
On hand / on order
0 / 74,748
next delivery 06 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
18,792
safety stock 12,084
Rec. Max
21,210
order qty 2,418
Service level
99.5%
stockout risk now 0%
Unit price
Rp 190,717
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 31 issue days in the last 180 days, last issue 4 days ago, 125 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 7 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (10,850 units) excluded from the baseline.
Demand pattern Erratic · 90 issue days · 21 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 52.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 16 functional locations
12 with criticality A/B · 15,984 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 50 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 400 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 50 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 5,037 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 400 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 1,500 | 29 | 11.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 400 | 28 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 120 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 400 | 23 | 9.01 |
| PX_BF-104-BRN08 COIL OUTLET BF-104 | A | 5,037 | 2 | 1.30 |
| PX_BF-102-QF26 BURNER BF-102 | A | 120 | 0 | 0.45 |
| PX_BF-111-PD31 CONVECTION SECTION | A | 400 | 0 | 0.45 |
Lead time and procurement
Lead time 84 ± 52 days (PO history, 27 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 16 Sept 2026 | PR03 Regular replenishment | 22,389 | Rp 197,379 | 20 Dec 2026 open | 95 d |
| 11 Aug 2026 | PR06 Regular replenishment | 17,642 | Rp 192,128 | 06 Oct 2026 open | 56 d |
| 16 Jul 2026 | PR03 Regular replenishment | 22,997 | Rp 188,805 | 07 Oct 2026 open | 83 d |
| 09 Jul 2026 | PR05 Project / turnaround | 11,720 | Rp 193,538 | 27 Jan 2027 open | 202 d |
| 11 Jun 2026 | PR06 Regular replenishment | 28,368 | Rp 189,414 | 08 Aug 2026 | 58 d |
| 09 May 2026 | PR05 Project / turnaround | 39,555 | Rp 196,271 | 07 Aug 2026 | 90 d |
| 05 Apr 2026 | PR04 Regular (other) | 30,506 | Rp 194,761 | 22 Jun 2026 | 78 d |
| 22 Mar 2026 | PR06 Regular replenishment | 10,857 | Rp 182,007 | 31 Jul 2026 | 131 d |
| 17 Mar 2026 | PR06 Regular replenishment | 12,623 | Rp 193,659 | 19 May 2026 | 63 d |
| 12 Mar 2026 | PR06 Regular replenishment | 17,489 | Rp 185,516 | 29 Apr 2026 | 48 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 27 Sept 2026 | 200 | 201000031834 | Corrective |
| 26 Sept 2026 | 50 | 201000005210 | Corrective |
| 25 Sept 2026 | 50 | 209000029477 | Other maintenance |
| 15 Sept 2026 | 200 | 201000023637 | Corrective |
| 04 Sept 2026 | 50 | 201000024613 | Corrective |
| 04 Sept 2026 | 1,500 | 204000038666 | Preventive |
| 21 Aug 2026 | 50 | 201000007325 | Corrective |
| 20 Aug 2026 | 600 | 201000019311 | Corrective |
| 12 Aug 2026 | 1,500 | 201000019676 | Corrective |
| 05 Aug 2026 | 600 | 201000036260 | Corrective |
| 01 Aug 2026 | 200 | 201000026506 | Corrective |
| 31 Jul 2026 | 50 | 201000003587 | Corrective |
| 28 Jul 2026 | 50 | 201000009431 | Corrective |
| 25 Jul 2026 | 600 | 201000020588 | Corrective |
| 22 Jul 2026 | 5,700 | 201000024568 | Corrective |