Sparely
DU

FIREBRICK,INSUL,28,65T,114W,230L

Material 4100071552 · FIREBRICK · Plant 1000

ALong-leadMonitorStockout
Material
4100071552
Category
FIREBRICK
Base unit
EA
MRP type
Non Stock
Criticality
A (12 of 16 FuncLocs A/B)
Supplier
CAHAYA LOGAM PRATAMA PT
Lead time
84 d · P80 118 d
Unit price
Rp 190,717

Recommendation

  • 1.Forecast 29,012 EA/year: 29,012 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~84 days; expected demand during lead time 6,709.
  • 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 18,792, order up to 21,210.
  • 4.Long lead time: 80% of deliveries took up to 118 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 16 FuncLoc(s), 12 of them criticality A/B.
  • 6.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 4,950Single sourceAbnormal consumptionOpen POSame description as 9 other material numbers
On hand / on order
0 / 74,748
next delivery 06 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
18,792
safety stock 12,084
Rec. Max
21,210
order qty 2,418
Service level
99.5%
stockout risk now 0%
Unit price
Rp 190,717
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 31 issue days in the last 180 days, last issue 4 days ago, 125 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 7 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (10,850 units) excluded from the baseline.

Demand pattern Erratic · 90 issue days · 21 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 52.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 16 functional locations

12 with criticality A/B · 15,984 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A5011442.86
PX_BF-106
CRACKING FURNACE BF-106
A4008230.86
PX_BF-112
CRACKING FURNACE BF-112
A507327.01
PX_BF-102
CRACKING FURNACE BF-102
A5,0377128.72
PX_BF-103
CRACKING FURNACE BF-103
A4003814.58
PX_BF-109
CRACKING FURNACE BF-109
A1,5002911.58
PX_BF-104
CRACKING FURNACE BF-104
A4002811.58
PX_BF-107
CRACKING FURNACE BF-107
A120239.01
PX_BF-111
CRACKING FURNACE BF-111
A400239.01
PX_BF-104-BRN08
COIL OUTLET BF-104
A5,03721.30
PX_BF-102-QF26
BURNER BF-102
A12000.45
PX_BF-111-PD31
CONVECTION SECTION
A40000.45

Lead time and procurement

Lead time 84 ± 52 days (PO history, 27 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
16 Sept 2026PR03
Regular replenishment
22,389Rp 197,37920 Dec 2026
open
95 d
11 Aug 2026PR06
Regular replenishment
17,642Rp 192,12806 Oct 2026
open
56 d
16 Jul 2026PR03
Regular replenishment
22,997Rp 188,80507 Oct 2026
open
83 d
09 Jul 2026PR05
Project / turnaround
11,720Rp 193,53827 Jan 2027
open
202 d
11 Jun 2026PR06
Regular replenishment
28,368Rp 189,41408 Aug 202658 d
09 May 2026PR05
Project / turnaround
39,555Rp 196,27107 Aug 202690 d
05 Apr 2026PR04
Regular (other)
30,506Rp 194,76122 Jun 202678 d
22 Mar 2026PR06
Regular replenishment
10,857Rp 182,00731 Jul 2026131 d
17 Mar 2026PR06
Regular replenishment
12,623Rp 193,65919 May 202663 d
12 Mar 2026PR06
Regular replenishment
17,489Rp 185,51629 Apr 202648 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026LowPX_BF-112Painting BF-112
28 Sept 2026LowPX_BF-106Peep door broken BF-106
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107

Recent goods issues

Posting dateQtyOrderOrder type
27 Sept 2026200201000031834Corrective
26 Sept 202650201000005210Corrective
25 Sept 202650209000029477Other maintenance
15 Sept 2026200201000023637Corrective
04 Sept 202650201000024613Corrective
04 Sept 20261,500204000038666Preventive
21 Aug 202650201000007325Corrective
20 Aug 2026600201000019311Corrective
12 Aug 20261,500201000019676Corrective
05 Aug 2026600201000036260Corrective
01 Aug 2026200201000026506Corrective
31 Jul 202650201000003587Corrective
28 Jul 202650201000009431Corrective
25 Jul 2026600201000020588Corrective
22 Jul 20265,700201000024568Corrective