FIREBRICK,INSUL,23,76T,114W,230L
Material 4100071553 · FIREBRICK · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100071553
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (10 of 13 FuncLocs A/B)
- Supplier
- MEGA ENERGI ABADI PT
- Lead time
- 117 d · P80 163 d
- Unit price
- Rp 187,573
Recommendation
- 1.Forecast 14,708 EA/year: 14,708 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~117 days; expected demand during lead time 4,703.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 12,242, order up to 13,468.
- 4.Long lead time: 80% of deliveries took up to 163 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 13 FuncLoc(s), 10 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 8,650Single sourceAbnormal consumptionOpen POSame description as 8 other material numbers
On hand / on order
2,676 / 15,559
next delivery 02 Oct 2026
Today Min / Max
2,000 / 3,344
static parameters in BoM
Rec. Min (reorder point)
12,242
safety stock 7,540
Rec. Max
13,468
order qty 1,226
Service level
99.5%
stockout risk now 0%
Unit price
Rp 187,573
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 14 issue days in the last 180 days, last issue 1 days ago, 101 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 6 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9,150 units) excluded from the baseline.
Demand pattern Erratic · 49 issue days · 12 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 27.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 13 functional locations
10 with criticality A/B · 18,601 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1,500 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 400 | 82 | 30.86 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 120 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 400 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 400 | 29 | 11.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 5,037 | 28 | 11.58 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 400 | 23 | 9.01 |
| PX_BF-112-QF16 QO TO QUENCH FITTING | A | 5,037 | 5 | 1.73 |
| PX_BF-108-COIL32 CONVECTION SECTION | B | 50 | 0 | 0.45 |
| PX_BF-109-PD09 CONVECTION SECTION | B | 50 | 0 | 0.45 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 50 | 41 | 14.58 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 120 | 8 | 3.02 |
Lead time and procurement
Lead time 117 ± 56 days (PO history, 15 PO lines) · on-time 40%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Jul 2026 | PR03 Regular replenishment | 9,625 | Rp 181,445 | 16 Nov 2026 open | 128 d |
| 29 Jun 2026 | PR06 Regular replenishment | 5,712 | Rp 187,573 | 25 Sept 2026 | 88 d |
| 20 Jun 2026 | PR03 Regular replenishment | 9,959 | Rp 192,606 | 29 Aug 2026 | 70 d |
| 31 May 2026 | PR06 Regular replenishment | 12,306 | Rp 186,870 | 02 Sept 2026 | 94 d |
| 10 Apr 2026 | PR06 Regular replenishment | 6,932 | Rp 181,344 | 19 Sept 2026 | 162 d |
| 09 Apr 2026 | PR03 Regular replenishment | 5,934 | Rp 190,885 | 02 Oct 2026 open | 176 d |
| 01 Apr 2026 | PR06 Regular replenishment | 6,849 | Rp 190,017 | 21 Aug 2026 | 142 d |
| 11 Mar 2026 | PR06 Regular replenishment | 17,326 | Rp 187,963 | 19 Jun 2026 | 100 d |
| 30 Dec 2025 | PR04 Regular (other) | 11,011 | Rp 195,997 | 11 May 2026 | 132 d |
| 23 Dec 2025 | PR03 Regular replenishment | 15,317 | Rp 185,564 | 07 Apr 2026 | 105 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112-QF16 | Thermograph wall BF-112-QF16 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 50 | 201000007314 | Corrective |
| 30 Sept 2026 | 50 | 201000024363 | Corrective |
| 26 Sept 2026 | 600 | 201000025207 | Corrective |
| 29 Aug 2026 | 200 | 201000004962 | Corrective |
| 20 Aug 2026 | 1,500 | 201000007325 | Corrective |
| 28 Jul 2026 | 1,500 | 201000017737 | Corrective |
| 16 Jul 2026 | 50 | 201000025691 | Corrective |
| 08 Jul 2026 | 200 | 201000020343 | Corrective |
| 08 Jul 2026 | 200 | 204000027608 | Preventive |
| 06 Jul 2026 | 200 | 201000028383 | Corrective |
| 18 Jun 2026 | 200 | 201000022104 | Corrective |
| 11 Jun 2026 | 50 | 201000006766 | Corrective |
| 01 Jun 2026 | 200 | 201000032841 | Corrective |
| 17 May 2026 | 200 | 201000001121 | Corrective |
| 10 May 2026 | 5,700 | 201000002115 | Corrective |