FIREBRICK,INSUL,23,65T,114W,230L
Material 4100071591 · FIREBRICK · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100071591
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 11 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 91 d · P80 129 d
- Unit price
- Rp 50,487
Recommendation
- 1.Forecast 7,944 EA/year: 7,944 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~91 days; expected demand during lead time 1,974.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6,461, order up to 7,998.
- 4.Long lead time: 80% of deliveries took up to 129 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 11 FuncLoc(s), 6 of them criticality A/B.
- 6.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 2,950Single sourceAbnormal consumptionOpen POSame description as 8 other material numbers
On hand / on order
2,942 / 8,161
next delivery 01 Nov 2026
Today Min / Max
2,000 / 3,344
static parameters in BoM
Rec. Min (reorder point)
6,461
safety stock 4,487
Rec. Max
7,998
order qty 1,537
Service level
99.9%
stockout risk now 0%
Unit price
Rp 50,487
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 7 issue days in the last 180 days, last issue 47 days ago, 73 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (4,450 units) excluded from the baseline.
Demand pattern Erratic · 40 issue days · 5 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 19.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 11 functional locations
6 with criticality A/B · 20,701 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-102 CRACKING FURNACE BF-102 | A | 120 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1,500 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 400 | 29 | 11.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 400 | 28 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 120 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1,500 | 23 | 9.01 |
| PX_BF-104-DUCT34 CONVECTION SECTION | C | 5,037 | 2 | 0.87 |
| PX_BF-107-PD35 PEEP DOOR | C | 5,037 | 0 | 0.45 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 5,037 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 50 | 23 | 9.44 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 1,500 | 8 | 3.02 |
Lead time and procurement
Lead time 91 ± 43 days (PO history, 11 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 01 Sept 2026 | PR06 Regular replenishment | 8,161 | Rp 51,117 | 01 Nov 2026 open | 61 d |
| 02 Aug 2026 | PR06 Regular replenishment | 5,790 | Rp 50,487 | 19 Sept 2026 | 48 d |
| 12 Mar 2026 | PR03 Regular replenishment | 9,821 | Rp 50,023 | 12 May 2026 | 61 d |
| 18 Jan 2026 | PR03 Regular replenishment | 5,753 | Rp 50,946 | 19 Mar 2026 | 60 d |
| 02 Jan 2026 | PR06 Regular replenishment | 10,886 | Rp 48,770 | 12 Mar 2026 | 69 d |
| 17 Nov 2025 | PR03 Regular replenishment | 3,427 | Rp 48,009 | 26 Mar 2026 | 129 d |
| 12 Nov 2025 | PR03 Regular replenishment | 4,261 | Rp 50,931 | 22 Apr 2026 | 161 d |
| 04 Aug 2025 | PR03 Regular replenishment | 5,115 | Rp 50,773 | 25 Nov 2025 | 113 d |
| 01 Jul 2025 | PR03 Regular replenishment | 6,015 | Rp 50,590 | 12 Dec 2025 | 164 d |
| 06 Jun 2025 | PR06 Regular replenishment | 7,646 | Rp 49,094 | 21 Aug 2025 | 76 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Aug 2026 | 200 | 204000039855 | Preventive |
| 25 Jul 2026 | 200 | 201000034014 | Corrective |
| 16 Jul 2026 | 200 | 201000016046 | Corrective |
| 25 Jun 2026 | 600 | 201000031485 | Corrective |
| 19 Jun 2026 | 200 | 209000016742 | Other maintenance |
| 12 Jun 2026 | 200 | 201000016515 | Corrective |
| 13 Apr 2026 | 200 | 201000010885 | Corrective |
| 13 Apr 2026 | 200 | 201000021986 | Corrective |
| 10 Mar 2026 | 1,500 | 203000020244 | Turnaround |
| 09 Mar 2026 | 200 | 201000023649 | Corrective |
| 27 Feb 2026 | 50 | 201000027080 | Corrective |
| 24 Feb 2026 | 1,500 | 201000005954 | Corrective |
| 17 Feb 2026 | 200 | 201000002211 | Corrective |
| 04 Feb 2026 | 600 | 201000000182 | Corrective |
| 03 Feb 2026 | 200 | 201000019813 | Corrective |