FIREBRICK,INSUL,26,76T,114W,230L
Material 4100071636 · FIREBRICK · Plant 1000
ALong-leadTransferCriticalBelow reorder point
- Material
- 4100071636
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- CAHAYA INDUSTRI JAYA PT
- Lead time
- 74 d · P80 125 d
- Unit price
- Rp 82,297
Recommendation
- 1.Forecast 8,229 EA/year: 8,229 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~74 days; expected demand during lead time 1,664.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6,763, order up to 7,988.
- 4.On hand 67 + on order 3,852 is at or below the reorder point: 4,069 needed.
- 5.Long lead time: 80% of deliveries took up to 125 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
- 7.ML early warning: 98% probability of demand in the next 90 days.
- 8.Identical part 4100072068, 4100072203 holds spare stock: transfer 4069 EA instead of buying — no purchase needed.
Long-leadML early warningConvert to Stock ItemLast turnaround used 200Single sourceAbnormal consumptionOpen POSame description as 6 other material numbers
On hand / on order
67 / 3,852
next delivery 21 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6,763
safety stock 5,100
Rec. Max
7,988
order qty 1,225
Service level
99.9%
stockout risk now 9%
Unit price
Rp 82,297
PO history
ML early warning: 98% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 5 days ago, 70 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (5,900 units) excluded from the baseline.
Demand pattern Smooth · 22 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 14.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 5 functional locations
4 with criticality A/B · 1,910 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1,500 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 120 | 82 | 30.86 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 50 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 120 | 38 | 14.58 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 120 | 8 | 3.02 |
Lead time and procurement
Lead time 74 ± 53 days (PO history, 8 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 26 Jul 2026 | PR06 Regular replenishment | 6,236 | Rp 78,424 | 23 Aug 2026 | 28 d |
| 16 Jul 2026 | PR10 Other | 3,852 | Rp 83,362 | 21 Dec 2026 open | 158 d |
| 22 Jun 2026 | PR06 Regular replenishment | 3,017 | Rp 81,319 | 10 Jul 2026 | 18 d |
| 17 May 2026 | PR05 Project / turnaround | 5,792 | Rp 81,436 | 13 Aug 2026 | 88 d |
| 06 Apr 2026 | PR06 Regular replenishment | 6,704 | Rp 83,443 | 06 May 2026 | 30 d |
| 29 Dec 2025 | PR03 Regular replenishment | 7,285 | Rp 83,157 | 03 Feb 2026 | 36 d |
| 26 Jun 2025 | PR06 Regular replenishment | 3,229 | Rp 83,857 | 11 Sept 2025 | 77 d |
| 22 May 2025 | PR01 Import / long-lead | 3,815 | Rp 81,432 | 18 Oct 2025 | 149 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Sept 2026 | 200 | 201000005210 | Corrective |
| 05 Sept 2026 | 600 | 201000004876 | Corrective |
| 27 Jul 2026 | 600 | 201000009720 | Corrective |
| 21 Jun 2026 | 200 | 209000016742 | Other maintenance |
| 12 Jun 2026 | 600 | 209000014321 | Other maintenance |
| 27 Mar 2026 | 50 | 201000010780 | Corrective |
| 20 Mar 2026 | 600 | 201000005983 | Corrective |
| 23 Feb 2026 | 600 | 201000027766 | Corrective |
| 17 Feb 2026 | 600 | 201000030270 | Corrective |
| 31 Jan 2026 | 200 | 201000036633 | Corrective |
| 25 Jan 2026 | 600 | 201000019717 | Corrective |
| 12 Jan 2026 | 600 | 201000000139 | Corrective |
| 20 Dec 2025 | 600 | 201000020724 | Corrective |
| 20 Dec 2025 | 1,500 | 204000014453 | Preventive |
| 07 Nov 2025 | 200 | 203000026396 | Turnaround |