FIREBRICK,INSUL,23,65T,114W,230L
Material 4100071686 · FIREBRICK · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100071686
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 5 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 97 d · P80 134 d
- Unit price
- Rp 160,592
Recommendation
- 1.Forecast 2,946 EA/year: 2,946 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~97 days; expected demand during lead time 784.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2,751, order up to 3,276.
- 4.Long lead time: 80% of deliveries took up to 134 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
- 6.ML early warning: 87% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 1,700Single sourceAbnormal consumptionOpen POSame description as 8 other material numbers
On hand / on order
2,516 / 2,875
next delivery 07 Oct 2026
Today Min / Max
2,000 / 3,344
static parameters in BoM
Rec. Min (reorder point)
2,751
safety stock 1,968
Rec. Max
3,276
order qty 525
Service level
100.0%
stockout risk now 0%
Unit price
Rp 160,592
PO history
ML early warning: 87% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 15 days ago, 31 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (2,300 units) excluded from the baseline.
Demand pattern Lumpy · 14 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 7.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 5 functional locations
2 with criticality A/B · 8,487 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-109 CRACKING FURNACE BF-109 | A | 400 | 29 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 50 | 23 | 9.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1,500 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 1,500 | 23 | 9.44 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 5,037 | 8 | 3.02 |
Lead time and procurement
Lead time 97 ± 39 days (PO history, 7 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 30 Jun 2026 | PR03 Regular replenishment | 1,379 | Rp 163,826 | 07 Oct 2026 open | 99 d |
| 05 May 2026 | PR01 Import / long-lead | 1,496 | Rp 154,864 | 08 Oct 2026 open | 156 d |
| 21 Apr 2026 | PR06 Regular replenishment | 1,542 | Rp 165,271 | 12 Jun 2026 | 52 d |
| 09 Apr 2026 | PR03 Regular replenishment | 2,239 | Rp 155,660 | 25 Jun 2026 | 77 d |
| 15 Nov 2025 | PR03 Regular replenishment | 1,049 | Rp 159,347 | 09 Mar 2026 | 114 d |
| 08 Jul 2025 | PR03 Regular replenishment | 1,554 | Rp 167,162 | 24 Nov 2025 | 139 d |
| 27 Jun 2025 | PR03 Regular replenishment | 2,837 | Rp 160,592 | 11 Oct 2025 | 106 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 16 Sept 2026 | 50 | 209000036917 | Other maintenance |
| 23 Jul 2026 | 600 | 201000024568 | Corrective |
| 30 Apr 2026 | 600 | 203000029810 | Turnaround |
| 16 Mar 2026 | 200 | 201000018815 | Corrective |
| 14 Feb 2026 | 50 | 201000032808 | Corrective |
| 20 Jan 2026 | 50 | 201000025132 | Corrective |
| 18 Jan 2026 | 600 | 201000018680 | Corrective |
| 10 Dec 2025 | 600 | 201000037297 | Corrective |
| 22 Nov 2025 | 200 | 203000038363 | Turnaround |
| 20 Nov 2025 | 1,500 | 203000038363 | Turnaround |
| 24 Aug 2025 | 50 | 201000039902 | Corrective |
| 23 Aug 2025 | 200 | 201000039859 | Corrective |
| 03 Aug 2025 | 50 | 201000038329 | Corrective |
| 18 Jul 2025 | 600 | 201000003403 | Corrective |
| 12 Jul 2025 | 1,500 | 209000011144 | Other maintenance |