FIREBRICK,INSUL,23,76T,114W,230L
Material 4100071719 · FIREBRICK · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100071719
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B)
- Supplier
- CAHAYA INDUSTRI JAYA PT
- Lead time
- 101 d · P80 151 d
- Unit price
- Rp 162,313
Recommendation
- 1.Forecast 2,606 EA/year: 2,606 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~101 days; expected demand during lead time 720.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 2,037, order up to 2,528.
- 4.Long lead time: 80% of deliveries took up to 151 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
- 6.ML early warning: 93% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceAbnormal consumptionOpen POSame description as 8 other material numbers
On hand / on order
646 / 2,533
next delivery 19 Oct 2026
Today Min / Max
288 / 614
static parameters in BoM
Rec. Min (reorder point)
2,037
safety stock 1,318
Rec. Max
2,528
order qty 491
Service level
99.7%
stockout risk now 0%
Unit price
Rp 162,313
PO history
ML early warning: 93% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 1 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1,500 units) excluded from the baseline.
Demand pattern Lumpy · 17 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 8.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 5 functional locations
3 with criticality A/B · 2,470 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-111 CRACKING FURNACE BF-111 | A | 50 | 23 | 9.01 |
| PX_BF-104-COIL06 COIL OUTLET BF-104 | A | 1,500 | 0 | 0.45 |
| PX_BF-112-COIL04 CONVECTION SECTION | B | 120 | 0 | 0.45 |
| PX_BF-103-BRN06 CONVECTION SECTION | C | 400 | 0 | 0.45 |
| PX_BF-111-COIL23 COIL OUTLET BF-111 | C | 400 | 0 | 0.45 |
Lead time and procurement
Lead time 101 ± 61 days (PO history, 9 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 31 Aug 2026 | PR03 Regular replenishment | 2,533 | Rp 161,614 | 19 Oct 2026 open | 49 d |
| 24 Feb 2026 | PR06 Regular replenishment | 1,169 | Rp 159,020 | 17 Jun 2026 | 113 d |
| 17 Dec 2025 | PR03 Regular replenishment | 2,741 | Rp 160,954 | 24 Jul 2026 | 219 d |
| 21 Oct 2025 | PR03 Regular replenishment | 2,422 | Rp 162,313 | 25 Nov 2025 | 35 d |
| 16 Aug 2025 | PR06 Regular replenishment | 1,668 | Rp 159,090 | 12 Nov 2025 | 88 d |
| 03 Aug 2025 | PR05 Project / turnaround | 816 | Rp 168,082 | 27 Feb 2026 | 208 d |
| 28 Jun 2025 | PR03 Regular replenishment | 2,652 | Rp 171,797 | 06 Oct 2025 | 100 d |
| 02 Jun 2025 | PR04 Regular (other) | 1,649 | Rp 168,179 | 18 Sept 2025 | 108 d |
| 24 May 2025 | PR03 Regular replenishment | 1,967 | Rp 167,704 | 25 Jul 2025 | 62 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 10 Sept 2026 | Medium | PX_BF-111 | Peep door broken BF-111 |
| 03 Aug 2026 | Medium | PX_BF-111 | Thermograph wall BF-111 |
| 11 Jul 2026 | Medium | PX_BF-111 | Thermograph wall BF-111 |
| 27 Jun 2026 | Medium | PX_BF-111 | Leak from packing |
| 08 May 2026 | Medium | PX_BF-111 | Repair refractory crack BF-111 |
| 20 Apr 2026 | Emergency | PX_BF-111 | Cleaning burner BF-111 |
| 16 Apr 2026 | Medium | PX_BF-111 | Replace lamp as per PM finding |
| 20 Mar 2026 | Medium | PX_BF-111 | Painting BF-111 |
| 06 Mar 2026 | Low | PX_BF-111 | Install cover plate for MCP cracking |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 200 | 201000028331 | Corrective |
| 11 Aug 2026 | 200 | 204000007036 | Preventive |
| 22 Jun 2026 | 600 | 201000001192 | Corrective |
| 06 Jun 2026 | 50 | 209000008419 | Other maintenance |
| 11 Mar 2026 | 50 | 201000029087 | Corrective |
| 10 Mar 2026 | 200 | 201000015564 | Corrective |
| 22 Jan 2026 | 600 | 201000001031 | Corrective |
| 18 Dec 2025 | 50 | 201000036582 | Corrective |
| 25 Nov 2025 | 200 | 201000004694 | Corrective |
| 21 Nov 2025 | 50 | 201000025223 | Corrective |
| 09 Oct 2025 | 200 | 201000015543 | Corrective |
| 18 Sept 2025 | 50 | 201000028860 | Corrective |
| 31 Jul 2025 | 600 | 201000013503 | Corrective |
| 31 Jul 2025 | 1,500 | 203000033054 | Turnaround |
| 25 Jul 2025 | 1,500 | 201000004405 | Corrective |