FIREBRICK,INSUL,28,76T,114W,230L
Material 4100071738 · FIREBRICK · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100071738
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- MITRA ENERGI PERSADA PT
- Lead time
- 92 d · P80 121 d
- Unit price
- Rp 176,016
Recommendation
- 1.Forecast 4,427 EA/year: 4,427 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~92 days; expected demand during lead time 1,121.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 3,057, order up to 3,672.
- 4.Long lead time: 80% of deliveries took up to 121 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 94% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 1,550Single sourceAbnormal consumptionOpen POSame description as 7 other material numbers
On hand / on order
418 / 2,931
next delivery 29 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3,057
safety stock 1,937
Rec. Max
3,672
order qty 615
Service level
99.5%
stockout risk now 0%
Unit price
Rp 176,016
PO history
ML early warning: 94% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 23 days ago, 29 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1,750 units) excluded from the baseline.
Demand pattern Lumpy · 14 issue days · 4 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 7.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 5 functional locations
4 with criticality A/B · 5,727 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-103 CRACKING FURNACE BF-103 | A | 50 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 5,037 | 29 | 11.58 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 120 | 23 | 9.01 |
| PX_BF-101-QF17 DILUTION STEAM TO MIXED FEED COIL | B | 120 | 0 | 0.45 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 400 | 23 | 9.44 |
Lead time and procurement
Lead time 92 ± 74 days (PO history, 7 PO lines) · on-time 24%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 23 Aug 2026 | PR06 Regular replenishment | 2,931 | Rp 176,016 | 29 Oct 2026 open | 67 d |
| 23 Feb 2026 | PR06 Regular replenishment | 4,577 | Rp 169,236 | 23 Apr 2026 | 59 d |
| 13 Feb 2026 | PR06 Regular replenishment | 4,301 | Rp 172,022 | 06 May 2026 | 82 d |
| 16 Nov 2025 | PR06 Regular replenishment | 6,201 | Rp 181,553 | 26 Dec 2025 | 40 d |
| 10 Sept 2025 | PR01 Import / long-lead | 5,334 | Rp 177,315 | 16 Jun 2026 | 279 d |
| 17 Jul 2025 | PR06 Regular replenishment | 4,188 | Rp 179,869 | 25 Nov 2025 | 131 d |
| 07 May 2025 | PR06 Regular replenishment | 4,981 | Rp 174,539 | 14 Jun 2025 | 38 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Sept 2026 | 600 | 201000002044 | Corrective |
| 11 Jul 2026 | 1,500 | 201000029268 | Corrective |
| 20 May 2026 | 50 | 201000006538 | Corrective |
| 09 Apr 2026 | 5,700 | 201000025692 | Corrective |
| 10 Feb 2026 | 200 | 201000014945 | Corrective |
| 04 Feb 2026 | 50 | 201000018202 | Corrective |
| 20 Jan 2026 | 50 | 203000029956 | Turnaround |
| 22 Dec 2025 | 200 | 201000038215 | Corrective |
| 18 Dec 2025 | 1,500 | 203000014056 | Turnaround |
| 31 Oct 2025 | 200 | 209000022917 | Other maintenance |
| 11 Sept 2025 | 50 | 201000024365 | Corrective |
| 02 Sept 2025 | 200 | 201000001736 | Corrective |
| 28 Aug 2025 | 50 | 201000015857 | Corrective |
| 25 Aug 2025 | 200 | 203000020904 | Turnaround |
| 15 Aug 2025 | 600 | 201000006125 | Corrective |