FIREBRICK,INSUL,26,65T,114W,230L
Material 4100071844 · FIREBRICK · Plant 1000
ALong-leadReorderCriticalCritical insurance spare
- Material
- 4100071844
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 80 d · P80 131 d
- Unit price
- Rp 157,612
Recommendation
- 1.Forecast 250 EA/year: 250 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~80 days; expected demand during lead time 55.
- 3.A 99.1% service level gives the lowest holding + downtime-risk cost: reorder at 396, order up to 792.
- 4.On hand 4 + on order 2 is at or below the reorder point: order 786 now.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Long lead time: 80% of deliveries took up to 131 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
- 8.ML early warning: 37% probability of demand in the next 90 days.
Proposed purchase requisition
786 EA
Rp 123.9M · order by 01 Oct 2026
Expected arrival ≈ 80 days
Long-leadML early warningSingle sourceOpen POSame description as 9 other material numbers
On hand / on order
4 / 2
next delivery 16 Dec 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
396
safety stock 341
Rec. Max
792
order qty 396
Service level
99.1%
stockout risk now 13%
Unit price
Rp 157,612
PO history
ML early warning: 37% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 12 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 494.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 2 functional locations
2 with criticality A/B · 1,900 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1,500 | 38 | 14.58 |
| PX_BF-112-COIL30 BURNER BF-112 | A | 400 | 2 | 0.87 |
Lead time and procurement
Lead time 80 ± 47 days (PO history + category, 2 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 04 Aug 2026 | PR04 Regular (other) | 2 | Rp 163,832 | 16 Dec 2026 open | 134 d |
| 02 Aug 2026 | PR06 Regular replenishment | 2 | Rp 151,392 | 11 Sept 2026 | 40 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
| 26 Aug 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 26 Aug 2026 | Medium | PX_BF-103 | Hot spot at convection BF-103 |
| 03 Aug 2026 | Medium | PX_BF-103 | Install scaffolding at BF-103 |
| 24 Jul 2026 | Medium | PX_BF-103 | Thermograph wall BF-103 |
| 23 Jul 2026 | Emergency | PX_BF-103 | Decoking follow up BF-103 |
Recent goods issues
Never issued in the 17-month history.