FIREBRICK,INSUL,26,76T,114W,230L
Material 4100072044 · FIREBRICK · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100072044
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 76 d · P80 131 d
- Unit price
- Rp 157,612 (est.)
Recommendation
- 1.Forecast 430 EA/year: 430 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~76 days; expected demand during lead time 90.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 791, order up to 1,187.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimatedSame description as 6 other material numbers
On hand / on order
47 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
791
safety stock 702
Rec. Max
1,187
order qty 396
Service level
99.8%
stockout risk now 20%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 18 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 851.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 3 functional locations
1 with criticality A/B · 850 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-107 CRACKING FURNACE BF-107 | A | 50 | 23 | 9.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 400 | 41 | 14.58 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 400 | 8 | 3.02 |
Lead time and procurement
Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 03 Sept 2026 | Low | PX_BF-110 | Hot spot at convection BF-110 |
| 03 Sept 2026 | Medium | PX_BF-110 | Thermograph wall BF-110 |
| 01 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
Recent goods issues
Never issued in the 17-month history.