FIREBRICK,INSUL,23,76T,114W,230L
Material 4100072111 · FIREBRICK · Plant 1000
ALong-leadMonitorCritical insurance spare
- Material
- 4100072111
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- SURYA SUPLINDO LESTARI PT
- Lead time
- 76 d · P80 131 d
- Unit price
- Rp 113,769
Recommendation
- 1.Forecast 187 EA/year: 187 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~76 days; expected demand during lead time 39.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 396, order up to 792.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Long lead time: 80% of deliveries took up to 131 days and the fastest seen in its category 37 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidateLong-leadSingle sourceSame description as 8 other material numbers
On hand / on order
8 / 0
no open PO
Today Min / Max
3 / 8
static parameters in BoM
Rec. Min (reorder point)
396
safety stock 358
Rec. Max
792
order qty 396
Service level
99.5%
stockout risk now 9%
Unit price
Rp 113,769
PO history
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 370.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 1 functional locations
1 with criticality A/B · 5,037 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-104 CRACKING FURNACE BF-104 | A | 5,037 | 28 | 11.58 |
Lead time and procurement
Lead time 76 ± 47 days (PO history + category, 1 PO lines) · on-time 0%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 27 Jun 2026 | PR05 Project / turnaround | 1 | Rp 113,769 | 10 Sept 2026 | 75 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 04 Sept 2026 | Medium | PX_BF-104 | Replace burner tip BF-104 |
| 01 Sept 2026 | Medium | PX_BF-104 | Install scaffolding at BF-104 |
| 29 Aug 2026 | High | PX_BF-104 | Leak from packing |
| 08 Aug 2026 | Low | PX_BF-104 | [MSI-B-26-MZB-191] Permanent repair |
| 04 Aug 2026 | Medium | PX_BF-104 | Thermograph wall BF-104 |
| 04 Aug 2026 | Medium | PX_BF-104 | Peep door broken BF-104 |
| 21 Jul 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
Recent goods issues
Never issued in the 17-month history.