FIREBRICK,INSUL,26,65T,114W,230L
Material 4100072158 · FIREBRICK · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100072158
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (3 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 76 d · P80 131 d
- Unit price
- Rp 157,612 (est.)
Recommendation
- 1.Forecast 1,095 EA/year: 1,095 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~76 days; expected demand during lead time 228.
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 1,186, order up to 1,582.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimatedSame description as 9 other material numbers
On hand / on order
503 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1,186
safety stock 958
Rec. Max
1,582
order qty 396
Service level
99.7%
stockout risk now 11%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 42 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 4 functional locations
3 with criticality A/B · 2,700 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 400 | 73 | 27.01 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1,500 | 38 | 14.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 400 | 28 | 11.58 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 400 | 41 | 14.58 |
Lead time and procurement
Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
Recent goods issues
Never issued in the 17-month history.