FIREBRICK,INSUL,26,65T,114W,230L

Material 4100072158 · FIREBRICK · Plant 1000

AMonitorCritical insurance spare
Material
4100072158
Category
FIREBRICK
Base unit
EA
MRP type
Non Stock
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
76 d · P80 131 d
Unit price
Rp 157,612 (est.)

Recommendation

  • 1.Forecast 1,095 EA/year: 1,095 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~76 days; expected demand during lead time 228.
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 1,186, order up to 1,582.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimatedSame description as 9 other material numbers
On hand / on order
503 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1,186
safety stock 958
Rec. Max
1,582
order qty 396
Service level
99.7%
stockout risk now 11%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 42 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 4 functional locations

3 with criticality A/B · 2,700 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-112
CRACKING FURNACE BF-112
A4007327.01
PX_BF-103
CRACKING FURNACE BF-103
A1,5003814.58
PX_BF-104
CRACKING FURNACE BF-104
A4002811.58
PX_BF-110
CRACKING FURNACE BF-110
S4004114.58

Lead time and procurement

Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
21 Sept 2026MediumPX_BF-104Cleaning burner BF-104
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112

Recent goods issues

Never issued in the 17-month history.