FIREBRICK,INSUL,28,76T,114W,230L

Material 4100072636 · FIREBRICK · Plant 1000

AMonitorCritical insurance spare
Material
4100072636
Category
FIREBRICK
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
76 d · P80 131 d
Unit price
Rp 157,612 (est.)

Recommendation

  • 1.Forecast 236 EA/year: 236 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~76 days; expected demand during lead time 49.
  • 3.A 99.3% service level gives the lowest holding + downtime-risk cost: reorder at 396, order up to 792.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimatedSame description as 7 other material numbers
On hand / on order
2 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
396
safety stock 347
Rec. Max
792
order qty 396
Service level
99.3%
stockout risk now 12%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 11 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 466.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 2 functional locations

1 with criticality A/B · 240 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-104
CRACKING FURNACE BF-104
A1202811.58
PX_BF-101
CRACKING FURNACE BF-101
S12083.02

Lead time and procurement

Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026MediumPX_BF-104Cleaning burner BF-104
16 Sept 2026MediumPX_BF-104Hot spot at convection BF-104
14 Sept 2026MediumPX_BF-101Replace lamp as per PM finding
13 Sept 2026LowPX_BF-104Install cover plate for MCP cracking
04 Sept 2026MediumPX_BF-104Replace burner tip BF-104
01 Sept 2026MediumPX_BF-104Install scaffolding at BF-104
29 Aug 2026HighPX_BF-104Leak from packing
16 Aug 2026MediumPX_BF-101Install scaffolding at BF-101
08 Aug 2026LowPX_BF-104[MSI-B-26-MZB-191] Permanent repair
04 Aug 2026MediumPX_BF-104Thermograph wall BF-104

Recent goods issues

Never issued in the 17-month history.