FIREBRICK,INSUL,23,76T,114W,230L
Material 4100072939 · FIREBRICK · Plant 1000
SReduceExcess
- Material
- 4100072939
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- S (0 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 76 d · P80 131 d
- Unit price
- Rp 157,612 (est.)
Recommendation
- 1.Forecast 942 EA/year: 942 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~76 days; expected demand during lead time 196.
- 3.A 74.3% service level gives the lowest holding + downtime-risk cost: reorder at 200, order up to 500.
- 4.Stock 4,726 exceeds the level to keep (500) by 4,226.
Price estimatedLead time estimatedSame description as 8 other material numbers
On hand / on order
4,726 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
200
safety stock 4
Rec. Max
500
order qty 300
Service level
74.3%
stockout risk now 0%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 5 days ago, 10 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 11.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~37 days.
Installed on 1 functional locations
0 with criticality A/B · 1,500 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1,500 | 41 | 14.58 |
Lead time and procurement
Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
| 03 Sept 2026 | Low | PX_BF-110 | Hot spot at convection BF-110 |
| 03 Sept 2026 | Medium | PX_BF-110 | Thermograph wall BF-110 |
| 01 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 30 Aug 2026 | Low | PX_BF-110 | Leak from packing |
| 07 Aug 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 07 Aug 2026 | Medium | PX_BF-110 | Painting BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Sept 2026 | 200 | 201000008900 | Corrective |