FIREBRICK,INSUL,28,76T,114W,230L
Material 4100073049 · FIREBRICK · Plant 1000
AMaintainCritical insurance spare
- Material
- 4100073049
- Category
- FIREBRICK
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 76 d · P80 131 d
- Unit price
- Rp 157,612 (est.)
Recommendation
- 1.Forecast 257 EA/year: 257 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~76 days; expected demand during lead time 53.
- 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 396, order up to 792.
- 4.No issue in 17 months, but it protects critical equipment: keep it.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimatedSame description as 7 other material numbers
On hand / on order
738 / 0
no open PO
Today Min / Max
10 / 26
static parameters in BoM
Rec. Min (reorder point)
396
safety stock 343
Rec. Max
792
order qty 396
Service level
99.2%
stockout risk now 1%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 12 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 508.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.
Installed on 2 functional locations
2 with criticality A/B · 520 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-103 CRACKING FURNACE BF-103 | A | 400 | 38 | 14.58 |
| PX_BF-105-PD33 QO TO QUENCH FITTING | A | 120 | 2 | 1.30 |
Lead time and procurement
Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
| 26 Aug 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 26 Aug 2026 | Medium | PX_BF-103 | Hot spot at convection BF-103 |
| 03 Aug 2026 | Medium | PX_BF-103 | Install scaffolding at BF-103 |
| 24 Jul 2026 | Medium | PX_BF-103 | Thermograph wall BF-103 |
| 23 Jul 2026 | Emergency | PX_BF-103 | Decoking follow up BF-103 |
Recent goods issues
Never issued in the 17-month history.