Sparely
DU

FIREBRICK,INSUL,28,65T,114W,230L

Material 4100073069 · FIREBRICK · Plant 1000

AReorderCriticalSlow-moving
Material
4100073069
Category
FIREBRICK
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
76 d · P80 131 d
Unit price
Rp 157,612 (est.)

Recommendation

  • 1.Forecast 1,806 EA/year: 1,806 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~76 days; expected demand during lead time 376.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,400, order up to 1,815.
  • 4.On hand 52 + on order 0 is at or below the reorder point: order 1,763 now.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
1,763 EA
Rp 277.9M · order by 01 Oct 2026
Expected arrival ≈ 76 days
Price estimatedLead time estimatedSame description as 9 other material numbers
On hand / on order
52 / 0
no open PO
Today Min / Max
39 / 70
static parameters in BoM
Rec. Min (reorder point)
1,400
safety stock 1,025
Rec. Max
1,815
order qty 415
Service level
99.9%
stockout risk now 85%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 269 days ago, 21 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 1 functional locations

1 with criticality A/B · 5,037 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-106
CRACKING FURNACE BF-106
A5,0378230.86

Lead time and procurement

Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
28 Sept 2026LowPX_BF-106Peep door broken BF-106
19 Sept 2026MediumPX_BF-106Cleaning burner BF-106
15 Sept 2026MediumPX_BF-106Install cover plate BF-106
14 Sept 2026LowPX_BF-106Peep door broken BF-106
10 Sept 2026MediumPX_BF-106Replace burner tip BF-106
08 Sept 2026LowPX_BF-106Leak from packing
08 Sept 2026MediumPX_BF-106Painting BF-106
03 Sept 2026MediumPX_BF-106Install cover plate for MCP cracking

Recent goods issues

Posting dateQtyOrderOrder type
05 Jan 2026200201000039015Corrective