CASTABLE,REFRACTORY,INSUL,1300DEG C
Material 4100073422 · CASTABLE · Plant 1000
AReduceExcess
- Material
- 4100073422
- Category
- CASTABLE
- Base unit
- KG
- MRP type
- Non Stock
- Criticality
- A (4 of 7 FuncLocs A/B)
- Supplier
- CAHAYA INDUSTRI JAYA PT
- Lead time
- 72 d · P80 87 d
- Unit price
- Rp 55,762
Recommendation
- 1.Forecast 1,947 KG/year: 1,947 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~72 days; expected demand during lead time 382.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,382, order up to 2,106.
- 4.Stock 4,406 exceeds the level to keep (2,106) by 2,300.
- 5.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 99% probability of demand in the next 90 days.
ML early warningConvert to Stock ItemLast turnaround used 850Single sourceAbnormal consumptionOpen POSame description as 3 other material numbers
On hand / on order
4,406 / 4,965
next delivery 26 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1,382
safety stock 1,001
Rec. Max
2,106
order qty 724
Service level
99.9%
stockout risk now 0%
Unit price
Rp 55,762
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 9 issue days in the last 180 days, last issue 19 days ago, 45 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1,050 units) excluded from the baseline.
Demand pattern Erratic · 33 issue days · 12 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 13.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~30 days.
Installed on 7 functional locations
4 with criticality A/B · 2,025 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1,200 | 114 | 42.86 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 25 | 23 | 9.01 |
| PX_BF-112-COIL19 CONVECTION SECTION | A | 50 | 0 | 0.45 |
| PX_BF-110-BRN23 QO TO QUENCH FITTING | B | 25 | 0 | 0.45 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 25 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 200 | 23 | 9.44 |
| PX_BF-109-PD08 COIL OUTLET BF-109 | S | 500 | 0 | 0.45 |
Lead time and procurement
Lead time 72 ± 42 days (PO history, 16 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 06 Jul 2026 | PR06 Regular replenishment | 6,613 | Rp 52,774 | 09 Sept 2026 | 65 d |
| 23 May 2026 | PR05 Project / turnaround | 4,965 | Rp 52,783 | 26 Dec 2026 open | 217 d |
| 14 May 2026 | PR03 Regular replenishment | 6,145 | Rp 56,893 | 06 Aug 2026 | 84 d |
| 21 Mar 2026 | PR06 Regular replenishment | 7,065 | Rp 57,350 | 31 May 2026 | 71 d |
| 20 Mar 2026 | PR06 Regular replenishment | 7,524 | Rp 52,758 | 15 Apr 2026 | 26 d |
| 15 Mar 2026 | PR06 Regular replenishment | 3,918 | Rp 54,242 | 20 May 2026 | 66 d |
| 25 Feb 2026 | PR06 Regular replenishment | 3,061 | Rp 55,807 | 22 Apr 2026 | 56 d |
| 22 Jan 2026 | PR06 Regular replenishment | 7,057 | Rp 57,152 | 19 Apr 2026 | 87 d |
| 13 Jan 2026 | PR06 Regular replenishment | 4,433 | Rp 53,437 | 10 Feb 2026 | 28 d |
| 18 Dec 2025 | PR06 Regular replenishment | 6,616 | Rp 56,148 | 13 Apr 2026 | 116 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 14 Sept 2026 | Low | PX_BF-105 | Install cover plate BF-105 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 12 Sept 2026 | 25 | 201000020197 | Corrective |
| 11 Sept 2026 | 25 | 201000017566 | Corrective |
| 28 Aug 2026 | 200 | 201000007926 | Corrective |
| 23 Jul 2026 | 200 | 201000017366 | Corrective |
| 04 Jul 2026 | 50 | 201000018095 | Corrective |
| 27 May 2026 | 25 | 201000029008 | Corrective |
| 09 May 2026 | 25 | 201000013238 | Corrective |
| 16 Apr 2026 | 200 | 205000011450 | Other maintenance |
| 09 Apr 2026 | 50 | 201000035410 | Corrective |
| 07 Mar 2026 | 200 | 201000036940 | Corrective |
| 28 Feb 2026 | 25 | 201000013980 | Corrective |
| 21 Feb 2026 | 1,000 | 201000033036 | Corrective |
| 24 Jan 2026 | 50 | 201000008178 | Corrective |
| 24 Jan 2026 | 1,000 | 201000038721 | Corrective |
| 22 Jan 2026 | 200 | 203000022287 | Turnaround |