CASTABLE,REFRACTORY,LW,1500DEG C

Material 4100073473 · CASTABLE · Plant 1000

ALong-leadReduceExcess
Material
4100073473
Category
CASTABLE
Base unit
KG
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
CAHAYA LOGAM PRATAMA PT
Lead time
170 d · P80 252 d
Unit price
Rp 52,878

Recommendation

  • 1.Forecast 1,232 KG/year: 1,232 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~170 days; expected demand during lead time 572.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,560, order up to 2,152.
  • 4.Stock 2,483 exceeds the level to keep (2,152) by 331.
  • 5.Long lead time: 80% of deliveries took up to 252 days and the fastest seen in its category 30 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
  • 7.ML early warning: 95% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 150Single sourceAbnormal consumptionOpen POSame description as 5 other material numbers
On hand / on order
2,483 / 2,390
next delivery 03 Jan 2027
Today Min / Max
1,106 / 2,133
static parameters in BoM
Rec. Min (reorder point)
1,560
safety stock 989
Rec. Max
2,152
order qty 592
Service level
99.9%
stockout risk now 0%
Unit price
Rp 52,878
PO history
ML early warning: 95% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 4 days ago, 39 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (150 units) excluded from the baseline.

Demand pattern Erratic · 22 issue days · 7 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 9.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~30 days.

Installed on 4 functional locations

3 with criticality A/B · 625 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A50011442.86
PX_BF-107
CRACKING FURNACE BF-107
A50239.01
PX_BF-111
CRACKING FURNACE BF-111
A25239.01
PX_BF-108
CRACKING FURNACE BF-108
S50239.44

Lead time and procurement

Lead time 170 ± 45 days (PO history, 5 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
11 Jul 2026PR03
Regular replenishment
799Rp 53,33217 Feb 2027
open
221 d
31 Mar 2026PR01
Import / long-lead
377Rp 55,93419 Feb 2027
open
325 d
09 Jan 2026PR03
Regular replenishment
403Rp 52,87830 Aug 2026233 d
01 Jan 2026PR03
Regular replenishment
363Rp 52,83403 Jan 2027
open
367 d
19 Dec 2025PR03
Regular replenishment
989Rp 52,32910 Aug 2026234 d
14 Sept 2025PR04
Regular (other)
851Rp 55,30706 Jul 2027
open
660 d
03 Jun 2025PR06
Regular replenishment
546Rp 52,80219 Nov 2025169 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
24 Sept 2026HighPX_BF-108Leak from packing
22 Sept 2026MediumPX_BF-111Install cover plate BF-111
20 Sept 2026MediumPX_BF-105Replace lamp as per PM finding
20 Sept 2026MediumPX_BF-105Install scaffolding at BF-105
14 Sept 2026LowPX_BF-105Install cover plate BF-105
13 Sept 2026MediumPX_BF-105Thermograph wall BF-105
10 Sept 2026MediumPX_BF-108[MSI-B-26-JJB-193] Permanent repair

Recent goods issues

Posting dateQtyOrderOrder type
27 Sept 202650201000034347Corrective
22 Sept 2026200201000011818Corrective
01 Aug 2026200201000008499Corrective
01 May 2026200201000025318Corrective
25 Feb 2026200201000000733Corrective
23 Feb 202650204000002755Preventive
06 Feb 202650201000001779Corrective
06 Feb 2026200201000014092Corrective
31 Jan 202650201000016498Corrective
12 Jan 202650201000032767Corrective
01 Jan 202625201000012015Corrective
26 Dec 202550203000001878Turnaround
24 Dec 202550203000001878Turnaround
22 Dec 202525201000035258Corrective
23 Nov 202550201000006247Corrective