CASTABLE,REFRACTORY,DENSE,1300DEG C
Material 4100073509 · CASTABLE · Plant 1000
ALong-leadReduceExcess
- Material
- 4100073509
- Category
- CASTABLE
- Base unit
- KG
- MRP type
- Stock Item
- Criticality
- A (4 of 6 FuncLocs A/B)
- Supplier
- CAHAYA INDUSTRI JAYA PT
- Lead time
- 79 d · P80 95 d
- Unit price
- Rp 27,231
Recommendation
- 1.Forecast 1,474 KG/year: 1,474 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~79 days; expected demand during lead time 319.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,336, order up to 2,238.
- 4.Stock 5,757 exceeds the level to keep (2,238) by 3,519.
- 5.Long lead time: 80% of deliveries took up to 95 days and the fastest seen in its category 30 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
- 7.ML early warning: 98% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 1,000Single sourceAbnormal consumptionOpen POSame description as 3 other material numbers
On hand / on order
5,757 / 13,088
next delivery 19 Oct 2026
Today Min / Max
1,950 / 3,344
static parameters in BoM
Rec. Min (reorder point)
1,336
safety stock 1,017
Rec. Max
2,238
order qty 902
Service level
99.9%
stockout risk now 0%
Unit price
Rp 27,231
PO history
ML early warning: 98% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 5 days ago, 49 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1,050 units) excluded from the baseline.
Demand pattern Erratic · 22 issue days · 8 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 10.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~30 days.
Installed on 6 functional locations
4 with criticality A/B · 7,475 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 50 | 114 | 42.86 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 200 | 28 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 3,000 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 3,000 | 23 | 9.01 |
| PX_BF-111-COIL23 COIL OUTLET BF-111 | C | 25 | 0 | 0.45 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 1,200 | 23 | 9.44 |
Lead time and procurement
Lead time 79 ± 62 days (PO history, 8 PO lines) · on-time 45%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 20 Aug 2026 | PR01 Import / long-lead | 6,369 | Rp 28,249 | 10 May 2027 open | 263 d |
| 10 Aug 2026 | PR03 Regular replenishment | 6,719 | Rp 28,046 | 19 Oct 2026 open | 70 d |
| 26 Apr 2026 | PR06 Regular replenishment | 5,441 | Rp 28,448 | 22 Jun 2026 | 57 d |
| 12 Apr 2026 | PR06 Regular replenishment | 2,253 | Rp 26,236 | 01 Aug 2026 | 111 d |
| 29 Jan 2026 | PR06 Regular replenishment | 6,624 | Rp 27,226 | 16 Mar 2026 | 46 d |
| 17 Nov 2025 | PR06 Regular replenishment | 6,760 | Rp 26,327 | 12 Jan 2026 | 56 d |
| 16 May 2025 | PR06 Regular replenishment | 4,879 | Rp 26,486 | 14 Jul 2025 | 59 d |
| 04 May 2025 | PR06 Regular replenishment | 5,492 | Rp 27,236 | 06 Jun 2025 | 33 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 14 Sept 2026 | Low | PX_BF-105 | Install cover plate BF-105 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Sept 2026 | 200 | 209000029477 | Other maintenance |
| 01 Aug 2026 | 25 | 201000004526 | Corrective |
| 25 Jul 2026 | 1,000 | 201000031151 | Corrective |
| 30 Jun 2026 | 25 | 201000029116 | Corrective |
| 30 Jun 2026 | 200 | 201000031423 | Corrective |
| 18 Jun 2026 | 25 | 201000017478 | Corrective |
| 13 Jun 2026 | 1,000 | 209000014321 | Other maintenance |
| 22 Apr 2026 | 25 | 201000020310 | Corrective |
| 18 Apr 2026 | 50 | 201000006270 | Corrective |
| 03 Feb 2026 | 50 | 201000016884 | Corrective |
| 26 Jan 2026 | 25 | 204000016196 | Preventive |
| 08 Jan 2026 | 25 | 201000004568 | Corrective |
| 08 Jan 2026 | 200 | 201000018942 | Corrective |
| 10 Dec 2025 | 5,000 | 201000004042 | Corrective |
| 06 Dec 2025 | 1,000 | 203000037280 | Turnaround |