CASTABLE,REFRACTORY,LW,1600DEG C
Material 4100073615 · CASTABLE · Plant 1000
ALong-leadMonitorStockout
- Material
- 4100073615
- Category
- CASTABLE
- Base unit
- KG
- MRP type
- Non Stock
- Criticality
- A (3 of 4 FuncLocs A/B)
- Supplier
- KARYA SEJAHTERA NUSANTARA PT
- Lead time
- 82 d · P80 116 d
- Unit price
- Rp 90,081
Recommendation
- 1.Forecast 2,786 KG/year: 2,786 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~82 days; expected demand during lead time 628.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1,975, order up to 2,657.
- 4.Long lead time: 80% of deliveries took up to 116 days and the fastest seen in its category 30 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
- 6.ML early warning: 87% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 75Single sourceAbnormal consumptionOpen POSame description as 3 other material numbers
On hand / on order
0 / 4,298
next delivery 07 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1,975
safety stock 1,347
Rec. Max
2,657
order qty 682
Service level
99.8%
stockout risk now 0%
Unit price
Rp 90,081
PO history
ML early warning: 87% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 111 days ago, 36 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (100 units) excluded from the baseline.
Demand pattern Lumpy · 8 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 6.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~30 days.
Installed on 4 functional locations
3 with criticality A/B · 6,400 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 3,000 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 200 | 71 | 28.72 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 200 | 28 | 11.58 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 3,000 | 8 | 3.02 |
Lead time and procurement
Lead time 82 ± 50 days (PO history, 7 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 05 Sept 2026 | PR06 Regular replenishment | 2,062 | Rp 90,081 | 07 Oct 2026 open | 32 d |
| 25 Aug 2026 | PR05 Project / turnaround | 2,236 | Rp 87,038 | 21 Mar 2027 open | 208 d |
| 02 Jan 2026 | PR06 Regular replenishment | 2,583 | Rp 90,219 | 16 Mar 2026 | 73 d |
| 19 Dec 2025 | PR06 Regular replenishment | 1,945 | Rp 85,777 | 25 Mar 2026 | 96 d |
| 03 Dec 2025 | PR06 Regular replenishment | 2,737 | Rp 91,166 | 26 Feb 2026 | 85 d |
| 02 Dec 2025 | PR03 Regular replenishment | 3,185 | Rp 89,906 | 05 Jan 2026 | 34 d |
| 17 Nov 2025 | PR06 Regular replenishment | 2,142 | Rp 93,053 | 18 Mar 2026 | 121 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 07 Sept 2026 | Low | PX_BF-102 | Thermograph wall BF-102 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 12 Jun 2026 | 1,000 | 201000038887 | Corrective |
| 30 Apr 2026 | 200 | 201000011527 | Corrective |
| 09 Mar 2026 | 25 | 203000020244 | Turnaround |
| 26 Feb 2026 | 50 | 201000037279 | Corrective |
| 03 Jan 2026 | 25 | 201000012050 | Corrective |
| 29 Dec 2025 | 50 | 203000016277 | Turnaround |
| 22 Dec 2025 | 25 | 203000001878 | Turnaround |
| 11 Dec 2025 | 25 | 201000008455 | Corrective |
| 18 Sept 2025 | 5,000 | 201000032231 | Corrective |
| 21 Aug 2025 | 1,000 | 201000000265 | Corrective |
| 21 Jul 2025 | 25 | 209000036039 | Other maintenance |