CASTABLE,REFRACTORY,INSUL,1300DEG C
Material 4100075099 · CASTABLE · Plant 1000
ATransferNormalBelow reorder point
- Material
- 4100075099
- Category
- CASTABLE
- Base unit
- KG
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 58 d · P80 92 d
- Unit price
- Rp 43,840 (est.)
Recommendation
- 1.Forecast 1,458 KG/year: 1,458 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~58 days; expected demand during lead time 232.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,538, order up to 2,245.
- 4.On hand 566 + on order 0 is at or below the reorder point: 1,679 needed.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
- 6.Identical part 4100073422 holds spare stock: transfer 1679 KG instead of buying — no purchase needed.
Price estimatedLead time estimatedSame description as 3 other material numbers
On hand / on order
566 / 0
no open PO
Today Min / Max
352 / 813
static parameters in BoM
Rec. Min (reorder point)
1,538
safety stock 1,307
Rec. Max
2,245
order qty 707
Service level
99.9%
stockout risk now 8%
Unit price
Rp 43,840
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 40 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Lumpy · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~30 days.
Installed on 2 functional locations
2 with criticality A/B · 550 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-107 CRACKING FURNACE BF-107 | A | 500 | 23 | 9.01 |
| PX_BF-111-BRN05 DILUTION STEAM TO MIXED FEED COIL | B | 50 | 1 | 0.45 |
Lead time and procurement
Lead time 58 ± 27 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 15 Aug 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 08 Aug 2026 | Low | PX_BF-107 | Cleaning burner BF-107 |
| 21 Jul 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 21 Jul 2026 | Medium | PX_BF-107 | Thermograph wall BF-107 |
| 18 Jul 2026 | Emergency | PX_BF-107 | Hot spot at convection BF-107 |
| 10 Jul 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 12 Apr 2026 | Medium | PX_BF-107 | Decoking follow up BF-107 |
| 07 Mar 2026 | Medium | PX_BF-107 | Thermograph wall BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Aug 2026 | 25 | 201000023798 | Corrective |
| 13 May 2025 | 1,000 | 201000028813 | Corrective |