CASTABLE,REFRACTORY,INSUL,1300DEG C

Material 4100075099 · CASTABLE · Plant 1000

ATransferNormalBelow reorder point
Material
4100075099
Category
CASTABLE
Base unit
KG
MRP type
Stock Item
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
58 d · P80 92 d
Unit price
Rp 43,840 (est.)

Recommendation

  • 1.Forecast 1,458 KG/year: 1,458 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~58 days; expected demand during lead time 232.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,538, order up to 2,245.
  • 4.On hand 566 + on order 0 is at or below the reorder point: 1,679 needed.
  • 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
  • 6.Identical part 4100073422 holds spare stock: transfer 1679 KG instead of buying — no purchase needed.
Price estimatedLead time estimatedSame description as 3 other material numbers
On hand / on order
566 / 0
no open PO
Today Min / Max
352 / 813
static parameters in BoM
Rec. Min (reorder point)
1,538
safety stock 1,307
Rec. Max
2,245
order qty 707
Service level
99.9%
stockout risk now 8%
Unit price
Rp 43,840
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 40 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Lumpy · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~30 days.

Installed on 2 functional locations

2 with criticality A/B · 550 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-107
CRACKING FURNACE BF-107
A500239.01
PX_BF-111-BRN05
DILUTION STEAM TO MIXED FEED COIL
B5010.45

Lead time and procurement

Lead time 58 ± 27 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
15 Aug 2026MediumPX_BF-107Hot spot at convection BF-107
08 Aug 2026LowPX_BF-107Cleaning burner BF-107
21 Jul 2026MediumPX_BF-107Replace lamp as per PM finding
21 Jul 2026MediumPX_BF-107Thermograph wall BF-107
18 Jul 2026EmergencyPX_BF-107Hot spot at convection BF-107
10 Jul 2026MediumPX_BF-107Hot spot at convection BF-107
12 Apr 2026MediumPX_BF-107Decoking follow up BF-107
07 Mar 2026MediumPX_BF-107Thermograph wall BF-107

Recent goods issues

Posting dateQtyOrderOrder type
22 Aug 202625201000023798Corrective
13 May 20251,000201000028813Corrective