CERAMIC FIBER,BLANKET,50T,96KG/M3,1260C
Material 4100075356 · CERAMIC FIBER · Plant 1000
ALong-leadTransferCriticalStockout
- Material
- 4100075356
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Non Stock
- Criticality
- A (6 of 9 FuncLocs A/B)
- Supplier
- PRIMA INSTRUMEN PERSADA PT
- Lead time
- 74 d · P80 102 d
- Unit price
- Rp 2.1M
Recommendation
- 1.Forecast 59 RL/year: 59 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~74 days; expected demand during lead time 12.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 36, order up to 57.
- 4.On hand 0 + on order 24 is at or below the reorder point: 33 needed.
- 5.Long lead time: 80% of deliveries took up to 102 days and the fastest seen in its category 25 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 9 FuncLoc(s), 6 of them criticality A/B.
- 7.ML early warning: 100% probability of demand in the next 90 days.
- 8.Identical part 4100075634 holds spare stock: transfer 33 RL instead of buying — no purchase needed.
Long-leadML early warningConvert to Stock ItemLast turnaround used 8Single sourceAbnormal consumptionOpen POSame description as 3 other material numbers
On hand / on order
0 / 24
next delivery 27 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
36
safety stock 25
Rec. Max
57
order qty 21
Service level
99.9%
stockout risk now 6%
Unit price
Rp 2.1M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 12 issue days in the last 180 days, last issue 5 days ago, 104 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 6 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (14 units) excluded from the baseline.
Demand pattern Smooth · 70 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 21.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 9 functional locations
6 with criticality A/B · 25 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 5 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 3 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 3 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 2 | 38 | 14.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 2 | 23 | 9.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 4 | 23 | 9.44 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 4 | 8 | 3.02 |
Lead time and procurement
Lead time 74 ± 37 days (PO history, 17 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Sept 2026 | PR06 Regular replenishment | 24 | Rp 2.1M | 27 Nov 2026 open | 66 d |
| 22 Jun 2026 | PR03 Regular replenishment | 40 | Rp 2.1M | 05 Aug 2026 | 44 d |
| 15 Jun 2026 | PR06 Regular replenishment | 46 | Rp 2.2M | 10 Jul 2026 | 25 d |
| 10 May 2026 | PR06 Regular replenishment | 41 | Rp 2.1M | 05 Sept 2026 | 118 d |
| 21 Apr 2026 | PR06 Regular replenishment | 45 | Rp 2.2M | 13 Jun 2026 | 53 d |
| 21 Apr 2026 | PR06 Regular replenishment | 35 | Rp 2.1M | 15 Jul 2026 | 85 d |
| 08 Jan 2026 | PR05 Project / turnaround | 32 | Rp 2.2M | 08 Jul 2026 | 181 d |
| 16 Dec 2025 | PR06 Regular replenishment | 59 | Rp 2.1M | 16 Feb 2026 | 62 d |
| 02 Dec 2025 | PR06 Regular replenishment | 18 | Rp 2.1M | 16 Feb 2026 | 76 d |
| 30 Nov 2025 | PR05 Project / turnaround | 34 | Rp 2.2M | 02 Feb 2026 | 64 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Sept 2026 | 2 | 201000005210 | Corrective |
| 10 Sept 2026 | 1 | 201000027353 | Corrective |
| 06 Sept 2026 | 1 | 203000008243 | Turnaround |
| 24 Jul 2026 | 2 | 201000027503 | Corrective |
| 23 Jul 2026 | 1 | 201000023809 | Corrective |
| 22 Jun 2026 | 1 | 201000023783 | Corrective |
| 21 Jun 2026 | 1 | 201000023783 | Corrective |
| 06 Jun 2026 | 2 | 201000024026 | Corrective |
| 05 Jun 2026 | 1 | 203000002440 | Turnaround |
| 18 May 2026 | 2 | 201000039669 | Corrective |
| 12 May 2026 | 1 | 201000016405 | Corrective |
| 25 Apr 2026 | 1 | 203000034130 | Turnaround |
| 19 Apr 2026 | 3 | 201000004473 | Corrective |
| 17 Apr 2026 | 1 | 201000032200 | Corrective |
| 15 Apr 2026 | 1 | 201000012582 | Corrective |