CERAMIC FIBER,BLANKET,25T,128KG/M3,1430C
Material 4100075429 · CERAMIC FIBER · Plant 1000
ALong-leadTransferCriticalStockout
- Material
- 4100075429
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Non Stock
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- CAHAYA INDUSTRI ABADI PT
- Lead time
- 102 d · P80 138 d
- Unit price
- Rp 834,616
Recommendation
- 1.Forecast 28 RL/year: 28 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~102 days; expected demand during lead time 7.9.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 24, order up to 47.
- 4.On hand 0 + on order 22 is at or below the reorder point: 25 needed.
- 5.Long lead time: 80% of deliveries took up to 138 days and the fastest seen in its category 25 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
- 7.ML early warning: 99% probability of demand in the next 90 days.
- 8.Identical part 4100075943, 4100076334, 4100076877 holds spare stock: transfer 25 RL instead of buying — no purchase needed.
Long-leadML early warningConvert to Stock ItemLast turnaround used 5Single sourceOpen POSame description as 6 other material numbers
On hand / on order
0 / 22
next delivery 06 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
24
safety stock 17
Rec. Max
47
order qty 23
Service level
99.9%
stockout risk now 0%
Unit price
Rp 834,616
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 7 issue days in the last 180 days, last issue 50 days ago, 24 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (8 units) excluded from the baseline.
Demand pattern Smooth · 35 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 11.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 3 functional locations
2 with criticality A/B · 11 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 3 | 73 | 27.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 5 | 23 | 9.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 3 | 41 | 14.58 |
Lead time and procurement
Lead time 102 ± 48 days (PO history, 15 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 24 Jun 2026 | PR06 Regular replenishment | 22 | Rp 823,052 | 06 Nov 2026 open | 135 d |
| 08 May 2026 | PR06 Regular replenishment | 16 | Rp 841,857 | 02 Sept 2026 | 117 d |
| 17 Apr 2026 | PR06 Regular replenishment | 24 | Rp 831,927 | 12 Aug 2026 | 117 d |
| 11 Apr 2026 | PR06 Regular replenishment | 18 | Rp 813,057 | 14 Sept 2026 | 156 d |
| 25 Mar 2026 | PR06 Regular replenishment | 9 | Rp 834,139 | 04 Jul 2026 | 101 d |
| 14 Mar 2026 | PR05 Project / turnaround | 11 | Rp 834,616 | 05 Aug 2026 | 144 d |
| 30 Jan 2026 | PR06 Regular replenishment | 7 | Rp 841,937 | 15 Jun 2026 | 136 d |
| 27 Dec 2025 | PR06 Regular replenishment | 25 | Rp 830,861 | 18 Feb 2026 | 53 d |
| 26 Nov 2025 | PR06 Regular replenishment | 10 | Rp 836,051 | 27 Jan 2026 | 62 d |
| 16 Nov 2025 | PR06 Regular replenishment | 11 | Rp 825,826 | 31 Jan 2026 | 76 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
| 10 Sept 2026 | Medium | PX_BF-111 | Peep door broken BF-111 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 12 Aug 2026 | 1 | 209000023087 | Other maintenance |
| 09 Aug 2026 | 1 | 201000006656 | Corrective |
| 27 Jul 2026 | 1 | 203000004330 | Turnaround |
| 28 Jun 2026 | 2 | 201000032450 | Corrective |
| 10 Jun 2026 | 2 | 204000023020 | Preventive |
| 08 Jun 2026 | 1 | 203000002440 | Turnaround |
| 03 Jun 2026 | 1 | 201000011358 | Corrective |
| 11 May 2026 | 1 | 201000010174 | Corrective |
| 02 May 2026 | 1 | 201000028818 | Corrective |
| 01 Apr 2026 | 2 | 201000033914 | Corrective |
| 31 Mar 2026 | 1 | 201000037731 | Corrective |
| 11 Mar 2026 | 2 | 201000025379 | Corrective |
| 14 Feb 2026 | 1 | 201000030744 | Corrective |
| 11 Feb 2026 | 1 | 201000032040 | Corrective |
| 03 Feb 2026 | 1 | 201000016884 | Corrective |