CERAMIC FIBER,BLANKET,50T,96KG/M3,1430C
Material 4100075497 · CERAMIC FIBER · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100075497
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Non Stock
- Criticality
- A (5 of 6 FuncLocs A/B)
- Supplier
- MEGA ENERGI ABADI PT
- Lead time
- 77 d · P80 101 d
- Unit price
- Rp 2.5M
Recommendation
- 1.Forecast 30 RL/year: 30 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~77 days; expected demand during lead time 6.4.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 21, order up to 35.
- 4.Long lead time: 80% of deliveries took up to 101 days and the fastest seen in its category 25 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 6 FuncLoc(s), 5 of them criticality A/B.
- 6.ML early warning: 99% probability of demand in the next 90 days.
Long-leadML early warningConvert to Stock ItemLast turnaround used 5Single sourceAbnormal consumptionOpen POSame description as 7 other material numbers
On hand / on order
13 / 25
next delivery 02 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
21
safety stock 15
Rec. Max
35
order qty 14
Service level
99.9%
stockout risk now 0%
Unit price
Rp 2.5M
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 9 issue days in the last 180 days, last issue 1 days ago, 84 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (6 units) excluded from the baseline.
Demand pattern Erratic · 24 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 11.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 6 functional locations
5 with criticality A/B · 17 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 4 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 4 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 2 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 3 | 71 | 28.72 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 3 | 23 | 9.44 |
Lead time and procurement
Lead time 77 ± 39 days (PO history, 15 PO lines) · on-time 40%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 15 Sept 2026 | PR05 Project / turnaround | 16 | Rp 2.4M | 06 Jan 2027 open | 113 d |
| 25 Jul 2026 | PR06 Regular replenishment | 9 | Rp 2.5M | 02 Oct 2026 open | 69 d |
| 11 Jun 2026 | PR04 Regular (other) | 9 | Rp 2.5M | 22 Aug 2026 | 72 d |
| 20 Feb 2026 | PR06 Regular replenishment | 16 | Rp 2.5M | 17 Apr 2026 | 56 d |
| 23 Jan 2026 | PR03 Regular replenishment | 18 | Rp 2.6M | 21 Mar 2026 | 57 d |
| 22 Jan 2026 | PR06 Regular replenishment | 9 | Rp 2.6M | 04 Mar 2026 | 41 d |
| 22 Jan 2026 | PR06 Regular replenishment | 12 | Rp 2.5M | 19 Mar 2026 | 56 d |
| 22 Nov 2025 | PR03 Regular replenishment | 18 | Rp 2.6M | 28 Feb 2026 | 98 d |
| 23 Oct 2025 | PR06 Regular replenishment | 8 | Rp 2.6M | 14 Dec 2025 | 52 d |
| 14 Oct 2025 | PR06 Regular replenishment | 13 | Rp 2.6M | 19 Feb 2026 | 128 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 1 | 201000010018 | Corrective |
| 22 Sept 2026 | 1 | 209000029477 | Other maintenance |
| 24 Jul 2026 | 2 | 201000002081 | Corrective |
| 26 Jun 2026 | 1 | 201000033706 | Corrective |
| 12 Jun 2026 | 1 | 201000023683 | Corrective |
| 27 May 2026 | 1 | 201000002230 | Corrective |
| 10 May 2026 | 1 | 201000011420 | Corrective |
| 08 May 2026 | 1 | 201000010542 | Corrective |
| 04 May 2026 | 2 | 201000036238 | Corrective |
| 21 Mar 2026 | 1 | 201000005983 | Corrective |
| 04 Mar 2026 | 1 | 201000011654 | Corrective |
| 22 Jan 2026 | 2 | 201000008172 | Corrective |
| 08 Jan 2026 | 1 | 201000024178 | Corrective |
| 08 Jan 2026 | 3 | 201000031110 | Corrective |
| 06 Jan 2026 | 2 | 201000024982 | Corrective |