CERAMIC FIBER,BLANKET,25T,128KG/M3,1260C
Material 4100075669 · CERAMIC FIBER · Plant 1000
AMonitorInsurance gap
- Material
- 4100075669
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Non Stock
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 57 d · P80 87 d
- Unit price
- Rp 1.3M (est.)
Recommendation
- 1.Forecast 2.6 RL/year: 2.6 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~57 days; expected demand during lead time 0.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimatedSame description as 6 other material numbers
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
7
order qty 3
Service level
100.0%
stockout risk now 26%
Unit price
Rp 1.3M
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 27 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 3 functional locations
2 with criticality A/B · 11 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-112 CRACKING FURNACE BF-112 | A | 2 | 73 | 27.01 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 4 | 28 | 11.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 5 | 23 | 9.44 |
Lead time and procurement
Lead time 57 ± 31 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 16 Sept 2026 | Medium | PX_BF-104 | Hot spot at convection BF-104 |
| 13 Sept 2026 | Low | PX_BF-104 | Install cover plate for MCP cracking |
| 10 Sept 2026 | Medium | PX_BF-108 | [MSI-B-26-JJB-193] Permanent repair |
Recent goods issues
Never issued in the 17-month history.