CERAMIC FIBER,BLANKET,50T,96KG/M3,1260C
Material 4100075746 · CERAMIC FIBER · Plant 1000
ATransferCriticalStockout
- Material
- 4100075746
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 57 d · P80 87 d
- Unit price
- Rp 1.3M (est.)
Recommendation
- 1.Forecast 3.4 RL/year: 3.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~57 days; expected demand during lead time 0.5.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
- 4.On hand 0 + on order 0 is at or below the reorder point: 8 needed.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
- 6.Identical part 4100075634 holds spare stock: transfer 8 RL instead of buying — no purchase needed.
Price estimatedLead time estimatedSame description as 3 other material numbers
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
100.0%
stockout risk now 41%
Unit price
Rp 1.3M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 437 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 1 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-109 CRACKING FURNACE BF-109 | A | 5 | 29 | 11.58 |
Lead time and procurement
Lead time 57 ± 31 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 03 Sept 2026 | Low | PX_BF-109 | Install scaffolding at BF-109 |
| 02 Sept 2026 | Low | PX_BF-109 | Install cover plate for MCP cracking |
| 16 Aug 2026 | Medium | PX_BF-109 | Install cover plate BF-109 |
| 13 Jul 2026 | Medium | PX_BF-109 | Cleaning burner BF-109 |
| 09 Jul 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 09 Jul 2026 | Low | PX_BF-109 | Leak from packing |
| 01 Jul 2026 | Emergency | PX_BF-109 | [MSI-B-26-YDN-280/M] Replace line |
| 23 Jun 2026 | High | PX_BF-109 | Cleaning burner BF-109 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Jul 2025 | 1 | 201000039372 | Corrective |