Sparely
DU

CERAMIC FIBER,BLANKET,50T,96KG/M3,1260C

Material 4100075886 · CERAMIC FIBER · Plant 1000

ATransferCriticalSlow-moving
Material
4100075886
Category
CERAMIC FIBER
Base unit
RL
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
MEGA ENERGI ABADI PT
Lead time
45 d · P80 87 d
Unit price
Rp 861,294

Recommendation

  • 1.Forecast 46 RL/year: 46 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~45 days; expected demand during lead time 5.7.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 21, order up to 50.
  • 4.On hand 3 + on order 0 is at or below the reorder point: 47 needed.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
  • 6.Identical part 4100075634 holds spare stock: transfer 47 RL instead of buying — no purchase needed.
Single sourceSame description as 3 other material numbers
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
21
safety stock 16
Rec. Max
50
order qty 29
Service level
99.9%
stockout risk now 57%
Unit price
Rp 861,294
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 293 days ago, 26 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.

Installed on 3 functional locations

2 with criticality A/B · 10 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-112
CRACKING FURNACE BF-112
A57327.01
PX_BF-109
CRACKING FURNACE BF-109
A22911.58
PX_BF-110
CRACKING FURNACE BF-110
S34114.58

Lead time and procurement

Lead time 45 ± 31 days (PO history + category, 2 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
24 Jul 2025PR03
Regular replenishment
1Rp 869,54825 Aug 202532 d
01 Jul 2025PR06
Regular replenishment
2Rp 853,03925 Jul 202524 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
20 Sept 2026MediumPX_BF-109Thermograph wall BF-109
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112
15 Sept 2026MediumPX_BF-110Decoking follow up BF-110
13 Sept 2026MediumPX_BF-109Install scaffolding at BF-109
11 Sept 2026MediumPX_BF-110Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
12 Dec 20253201000021360Corrective