CERAMIC FIBER,BLANKET,25T,128KG/M3,1430C

Material 4100075940 · CERAMIC FIBER · Plant 1000

AMaintainCritical insurance spare
Material
4100075940
Category
CERAMIC FIBER
Base unit
RL
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
TIRTA REFRAKTORI INTERNASIONAL PT
Lead time
86 d · P80 87 d
Unit price
Rp 1.3M

Recommendation

  • 1.Forecast 2.3 RL/year: 2.3 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~86 days; expected demand during lead time 0.5.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
  • 6.ML early warning: 33% probability of demand in the next 90 days.
ML early warningSingle sourceOpen POSame description as 6 other material numbers
On hand / on order
5 / 2
next delivery 13 Mar 2027
Today Min / Max
4 / 8
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
7
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.3M
PO history
ML early warning: 33% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 21 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 937.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.

Installed on 1 functional locations

1 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A511442.86

Lead time and procurement

Lead time 86 ± 31 days (PO history + category, 1 PO lines) · on-time 100%

PR dateTypeQtyUnit priceDeliveryLead time
20 Sept 2026PR06
Regular replenishment
2Rp 1.3M13 Mar 2027
open
174 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
20 Sept 2026MediumPX_BF-105Replace lamp as per PM finding
20 Sept 2026MediumPX_BF-105Install scaffolding at BF-105
14 Sept 2026LowPX_BF-105Install cover plate BF-105
13 Sept 2026MediumPX_BF-105Thermograph wall BF-105
06 Sept 2026MediumPX_BF-105Repair insulation BF-105
01 Sept 2026LowPX_BF-105Peep door broken BF-105
30 Aug 2026MediumPX_BF-105Painting BF-105
29 Aug 2026MediumPX_BF-105Leak from packing
27 Aug 2026MediumPX_BF-105Thermograph wall BF-105

Recent goods issues

Never issued in the 17-month history.