CERAMIC FIBER,BLANKET,25T,128KG/M3,1430C
Material 4100075940 · CERAMIC FIBER · Plant 1000
AMaintainCritical insurance spare
- Material
- 4100075940
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- TIRTA REFRAKTORI INTERNASIONAL PT
- Lead time
- 86 d · P80 87 d
- Unit price
- Rp 1.3M
Recommendation
- 1.Forecast 2.3 RL/year: 2.3 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~86 days; expected demand during lead time 0.5.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
- 4.No issue in 17 months, but it protects critical equipment: keep it.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
- 6.ML early warning: 33% probability of demand in the next 90 days.
ML early warningSingle sourceOpen POSame description as 6 other material numbers
On hand / on order
5 / 2
next delivery 13 Mar 2027
Today Min / Max
4 / 8
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
7
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.3M
PO history
ML early warning: 33% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 21 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 937.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 1 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 5 | 114 | 42.86 |
Lead time and procurement
Lead time 86 ± 31 days (PO history + category, 1 PO lines) · on-time 100%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 20 Sept 2026 | PR06 Regular replenishment | 2 | Rp 1.3M | 13 Mar 2027 open | 174 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 14 Sept 2026 | Low | PX_BF-105 | Install cover plate BF-105 |
| 13 Sept 2026 | Medium | PX_BF-105 | Thermograph wall BF-105 |
| 06 Sept 2026 | Medium | PX_BF-105 | Repair insulation BF-105 |
| 01 Sept 2026 | Low | PX_BF-105 | Peep door broken BF-105 |
| 30 Aug 2026 | Medium | PX_BF-105 | Painting BF-105 |
| 29 Aug 2026 | Medium | PX_BF-105 | Leak from packing |
| 27 Aug 2026 | Medium | PX_BF-105 | Thermograph wall BF-105 |
Recent goods issues
Never issued in the 17-month history.