CERAMIC FIBER,BLANKET,25T,96KG/M3,1260C
Material 4100076597 · CERAMIC FIBER · Plant 1000
ATransferNormalSlow-moving
- Material
- 4100076597
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Stock Item
- Criticality
- A (1 of 1 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 61 d · P80 87 d
- Unit price
- Rp 1.3M
Recommendation
- 1.Forecast 4.4 RL/year: 4.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~61 days; expected demand during lead time 0.7.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 9.
- 4.On hand 1 + on order 0 is at or below the reorder point: 8 needed.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
- 6.Identical part 4100076970 holds spare stock: transfer 8 RL instead of buying — no purchase needed.
Single sourceSame description as 7 other material numbers
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
9
order qty 5
Service level
99.9%
stockout risk now 17%
Unit price
Rp 1.3M
PO history
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 281 days ago, 12 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 1 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-103 CRACKING FURNACE BF-103 | A | 3 | 38 | 14.58 |
Lead time and procurement
Lead time 61 ± 31 days (PO history + category, 1 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Sept 2025 | PR01 Import / long-lead | 1 | Rp 1.3M | 24 Nov 2025 | 74 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
| 26 Aug 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 26 Aug 2026 | Medium | PX_BF-103 | Hot spot at convection BF-103 |
| 03 Aug 2026 | Medium | PX_BF-103 | Install scaffolding at BF-103 |
| 24 Jul 2026 | Medium | PX_BF-103 | Thermograph wall BF-103 |
| 23 Jul 2026 | Emergency | PX_BF-103 | Decoking follow up BF-103 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Dec 2025 | 1 | 201000004131 | Corrective |