BURNER TIP,TYPE DR852,A105

Material 4100077222 · BURNER TIP · Plant 1000

ALong-leadReorderCriticalSlow-moving
Material
4100077222
Category
BURNER TIP
Base unit
EA
MRP type
Stock Item
Criticality
A (7 of 10 FuncLocs A/B)
Supplier
MEGA ENERGI ABADI PT
Lead time
127 d · P80 204 d
Unit price
Rp 21.8M

Recommendation

  • 1.Forecast 30 EA/year: 30 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~127 days; expected demand during lead time 10.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 31, order up to 36.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 34 now.
  • 5.Long lead time: 80% of deliveries took up to 204 days and the fastest seen in its category 79 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 10 FuncLoc(s), 7 of them criticality A/B.
  • 7.ML early warning: 38% probability of demand in the next 90 days.
Proposed purchase requisition
34 EA
Rp 741.1M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Long-leadML early warningSingle source
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
31
safety stock 21
Rec. Max
36
order qty 5
Service level
99.9%
stockout risk now 90%
Unit price
Rp 21.8M
PO history
ML early warning: 38% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 240 days ago, 80 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 50.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.

Installed on 10 functional locations

7 with criticality A/B · 16 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A111442.86
PX_BF-102
CRACKING FURNACE BF-102
A17128.72
PX_BF-109
CRACKING FURNACE BF-109
A32911.58
PX_BF-104
CRACKING FURNACE BF-104
A12811.58
PX_BF-107
CRACKING FURNACE BF-107
A1239.01
PX_BF-111
CRACKING FURNACE BF-111
A1239.01
PX_BF-111-BRN10
BURNER BF-111
A300.45
PX_BF-101-COIL23
BURNER BF-101
C100.45
PX_BF-110
CRACKING FURNACE BF-110
S34114.58
PX_BF-108
CRACKING FURNACE BF-108
S1239.44

Lead time and procurement

Lead time 127 ± 68 days (PO history + category, 2 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
08 Apr 2026PR06
Regular replenishment
1Rp 21.7M25 Jun 202678 d
07 May 2025PR04
Regular (other)
2Rp 21.9M01 Nov 2025178 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
24 Sept 2026HighPX_BF-108Leak from packing
23 Sept 2026LowPX_BF-102Replace burner tip BF-102
22 Sept 2026MediumPX_BF-111Install cover plate BF-111
21 Sept 2026MediumPX_BF-104Cleaning burner BF-104
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
20 Sept 2026MediumPX_BF-105Replace lamp as per PM finding
20 Sept 2026MediumPX_BF-105Install scaffolding at BF-105

Recent goods issues

Posting dateQtyOrderOrder type
03 Feb 20261201000000182Corrective
19 Oct 20251201000025942Corrective