BURNER TIP,SIZE LI84,VITON

Material 4100077255 · BURNER TIP · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100077255
Category
BURNER TIP
Base unit
EA
MRP type
Non Stock
Criticality
A (3 of 9 FuncLocs A/B)
Supplier
CAHAYA LOGAM PRATAMA PT
Lead time
127 d · P80 204 d
Unit price
Rp 12.6M

Recommendation

  • 1.Forecast 12 EA/year: 12 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~127 days; expected demand during lead time 4.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 14, order up to 18.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 18 now.
  • 5.Long lead time: 80% of deliveries took up to 204 days and the fastest seen in its category 79 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 9 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
18 EA
Rp 226.1M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
14
safety stock 10
Rec. Max
18
order qty 4
Service level
100.0%
stockout risk now 91%
Unit price
Rp 12.6M
PO history
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 240 days ago, 45 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 19.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.

Installed on 9 functional locations

3 with criticality A/B · 15 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-103
CRACKING FURNACE BF-103
A13814.58
PX_BF-109
CRACKING FURNACE BF-109
A12911.58
PX_BF-104
CRACKING FURNACE BF-104
A12811.58
PX_BF-108-BRN36
DILUTION STEAM TO MIXED FEED COIL
C400.45
PX_BF-108-COIL19
COIL OUTLET BF-108
C100.45
PX_BF-110
CRACKING FURNACE BF-110
S24114.58
PX_BF-108
CRACKING FURNACE BF-108
S1239.44
PX_BF-104-DUCT20
BURNER BF-104
S100.45
PX_BF-111-PD03
COIL OUTLET BF-111
S300.45

Lead time and procurement

Lead time 127 ± 68 days (PO history + category, 2 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
05 Mar 2026PR06
Regular replenishment
1Rp 13.0M30 Jul 2026147 d
25 Jun 2025PR06
Regular replenishment
2Rp 12.1M09 Oct 2025106 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026HighPX_BF-108Leak from packing
21 Sept 2026MediumPX_BF-104Cleaning burner BF-104
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
20 Sept 2026MediumPX_BF-103Leak from packing
20 Sept 2026MediumPX_BF-109Thermograph wall BF-109
19 Sept 2026LowPX_BF-103Leak from packing
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
16 Sept 2026MediumPX_BF-104Hot spot at convection BF-104

Recent goods issues

Posting dateQtyOrderOrder type
03 Feb 20261201000000182Corrective
23 Jun 20251201000032173Corrective
22 Jun 20251201000032173Corrective