BURNER TIP,TYPE FE681,VITON
Material 4100077274 · BURNER TIP · Plant 1000
ALong-leadReorderCriticalBelow reorder point
- Material
- 4100077274
- Category
- BURNER TIP
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 8 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 120 d · P80 204 d
- Unit price
- Rp 39.9M
Recommendation
- 1.Forecast 37 EA/year: 37 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~120 days; expected demand during lead time 12.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 39, order up to 43.
- 4.On hand 3 + on order 0 is at or below the reorder point: order 40 now.
- 5.Long lead time: 80% of deliveries took up to 204 days and the fastest seen in its category 79 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 8 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
40 EA
Rp 1.6B · order by 01 Oct 2026
Expected arrival ≈ 120 days
Needs Management sign-off before it reaches the PR draft
Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
39
safety stock 27
Rec. Max
43
order qty 4
Service level
99.9%
stockout risk now 86%
Unit price
Rp 39.9M
PO history
ML early warning: 27% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 93 days ago, 70 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 62.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.
Installed on 8 functional locations
3 with criticality A/B · 11 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
| PX_BF-103-BRN17 BURNER BF-103 | C | 1 | 0 | 0.45 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 4 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 1 | 23 | 9.44 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 1 | 8 | 3.02 |
| PX_BF-105-BRN08 COIL OUTLET BF-105 | S | 1 | 4 | 1.30 |
Lead time and procurement
Lead time 120 ± 68 days (PO history + category, 1 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Oct 2025 | PR03 Regular replenishment | 2 | Rp 39.9M | 31 Jan 2026 | 101 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Jun 2026 | 1 | 201000022451 | Corrective |