BURNER TIP,SIZE IO362,GRAPHITE

Material 4100077281 · BURNER TIP · Plant 1000

AMonitorCritical insurance spare
Material
4100077281
Category
BURNER TIP
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 9 FuncLocs A/B)
Supplier
No PO history
Lead time
127 d · P80 204 d
Unit price
Rp 15.5M (est.)

Recommendation

  • 1.Forecast 2.5 EA/year: 2.5 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~127 days; expected demand during lead time 0.9.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 7.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 9 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
7
order qty 2
Service level
100.0%
stockout risk now 22%
Unit price
Rp 15.5M
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 34 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.

Installed on 9 functional locations

2 with criticality A/B · 12 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-112
CRACKING FURNACE BF-112
A17327.01
PX_BF-107
CRACKING FURNACE BF-107
A1239.01
PX_BF-102-BRN17
CONVECTION SECTION
C100.45
PX_BF-104-BRN14
DILUTION STEAM TO MIXED FEED COIL
C100.45
PX_BF-110-PD11
DILUTION STEAM TO MIXED FEED COIL
C100.45
PX_BF-110
CRACKING FURNACE BF-110
S14114.58
PX_BF-108
CRACKING FURNACE BF-108
S1239.44
PX_BF-108-QF21
CONVECTION SECTION
S400.45
PX_BF-111-DUCT16
CONVECTION SECTION
S100.45

Lead time and procurement

Lead time 127 ± 68 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
24 Sept 2026HighPX_BF-108Leak from packing
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112
15 Sept 2026MediumPX_BF-110Decoking follow up BF-110

Recent goods issues

Never issued in the 17-month history.