BURNER TIP,TYPE GP414,A105
Material 4100077316 · BURNER TIP · Plant 1000
AReorderCriticalBelow reorder point
- Material
- 4100077316
- Category
- BURNER TIP
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 6 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 127 d · P80 204 d
- Unit price
- Rp 15.5M (est.)
Recommendation
- 1.Forecast 32 EA/year: 32 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~127 days; expected demand during lead time 11.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 35, order up to 41.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 40 now.
- 5.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
40 EA
Rp 619.7M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
35
safety stock 24
Rec. Max
41
order qty 6
Service level
99.9%
stockout risk now 91%
Unit price
Rp 15.5M
Category + unit estimate
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 155 days ago, 51 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 53.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.
Installed on 6 functional locations
4 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 1 | 114 | 42.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 1 | 73 | 27.01 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 1 | 71 | 28.72 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 1 | 23 | 9.01 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 1 | 8 | 3.02 |
| PX_BF-108-PD27 DILUTION STEAM TO MIXED FEED COIL | S | 1 | 1 | 0.45 |
Lead time and procurement
Lead time 127 ± 68 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 20 Sept 2026 | Medium | PX_BF-105 | Replace lamp as per PM finding |
| 20 Sept 2026 | Medium | PX_BF-105 | Install scaffolding at BF-105 |
| 17 Sept 2026 | Medium | PX_BF-112 | Cleaning burner BF-112 |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 29 Apr 2026 | 1 | 201000023802 | Corrective |