BURNER TIP,SIZE SN730,CS

Material 4100077367 · BURNER TIP · Plant 1000

AReorderCriticalStockout
Material
4100077367
Category
BURNER TIP
Base unit
EA
MRP type
Non Stock
Criticality
A (3 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
127 d · P80 204 d
Unit price
Rp 15.5M (est.)

Recommendation

  • 1.Forecast 21 EA/year: 21 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~127 days; expected demand during lead time 7.3.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 25, order up to 30.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 30 now.
  • 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
30 EA
Rp 464.8M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
25
safety stock 18
Rec. Max
30
order qty 5
Service level
99.9%
stockout risk now 91%
Unit price
Rp 15.5M
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 113 days ago, 32 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 35.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.

Installed on 5 functional locations

3 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A111442.86
PX_BF-112
CRACKING FURNACE BF-112
A17327.01
PX_BF-111-COIL25
BURNER BF-111
A121.30
PX_BF-105-BRN15
PEEP DOOR
C110.45
PX_BF-108-BRN36
DILUTION STEAM TO MIXED FEED COIL
C100.45

Lead time and procurement

Lead time 127 ± 68 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
20 Sept 2026MediumPX_BF-105Replace lamp as per PM finding
20 Sept 2026MediumPX_BF-105Install scaffolding at BF-105
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112
14 Sept 2026LowPX_BF-105Install cover plate BF-105
13 Sept 2026MediumPX_BF-105Thermograph wall BF-105
06 Sept 2026MediumPX_BF-105Repair insulation BF-105

Recent goods issues

Posting dateQtyOrderOrder type
10 Jun 20261201000037228Corrective