BURNER TIP,TYPE PU42,INCOLOY
Material 4100077500 · BURNER TIP · Plant 1000
AReduceNon-moving
- Material
- 4100077500
- Category
- BURNER TIP
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 127 d · P80 204 d
- Unit price
- Rp 15.5M (est.)
Recommendation
- 1.Forecast 1.2 EA/year: 1.2 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~127 days; expected demand during lead time 0.4.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 4.Stock 14 exceeds the level to keep (5) by 9.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
14 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 15.5M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 19 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.
Installed on 3 functional locations
2 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 1 | 29 | 11.58 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 1 | 8 | 3.02 |
Lead time and procurement
Lead time 127 ± 68 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 20 Sept 2026 | Medium | PX_BF-109 | Thermograph wall BF-109 |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 13 Sept 2026 | Medium | PX_BF-109 | Install scaffolding at BF-109 |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
| 03 Sept 2026 | Low | PX_BF-109 | Install scaffolding at BF-109 |
| 02 Sept 2026 | Low | PX_BF-109 | Install cover plate for MCP cracking |
Recent goods issues
Never issued in the 17-month history.