BURNER TIP,TYPE JX553,INCOLOY

Material 4100077901 · BURNER TIP · Plant 1000

AReduceExcess
Material
4100077901
Category
BURNER TIP
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
No PO history
Lead time
127 d · P80 204 d
Unit price
Rp 15.5M (est.)

Recommendation

  • 1.Forecast 3.0 EA/year: 3.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~127 days; expected demand during lead time 1.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 7.
  • 4.Stock 48 exceeds the level to keep (7) by 41.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
48 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 4
Rec. Max
7
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 15.5M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 93 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 5.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-107
CRACKING FURNACE BF-107
A1239.01

Lead time and procurement

Lead time 127 ± 68 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
15 Aug 2026MediumPX_BF-107Hot spot at convection BF-107
08 Aug 2026LowPX_BF-107Cleaning burner BF-107
21 Jul 2026MediumPX_BF-107Replace lamp as per PM finding
21 Jul 2026MediumPX_BF-107Thermograph wall BF-107
18 Jul 2026EmergencyPX_BF-107Hot spot at convection BF-107
10 Jul 2026MediumPX_BF-107Hot spot at convection BF-107
12 Apr 2026MediumPX_BF-107Decoking follow up BF-107
07 Mar 2026MediumPX_BF-107Thermograph wall BF-107

Recent goods issues

Posting dateQtyOrderOrder type
30 Jun 20261201000031423Corrective